American Bar Association
Forum on the Construction Industry/TIPS
Fidelity & Surety
Law Committee
__________________________________________________
Withstanding the Tremors: The Golden Rules for
A Rock-Solid Design/Build Project
Learning from the Mistakes of
Others:
“When Design Build Has Gone Awry”
Part I
Deborah J.
Mackay
Faegre &
Benson LLP
2200 Wells
Fargo Center
Minneapolis MN
55402
January 25, 2007
The Westin St. Francis, San Francisco, CA
__________________________________________________
© 2007 American Bar Association
LEARNING FROM THE MISTAKES OF OTHERS:
WHEN DESIGN-BUILD HAS GONE AWRY
Deborah J. Mackay
This paper examines some of the
causes and consequences of errors during the procurement and proposal phase of
design-build projects. The common thread
linking the problems discussed below is a failure to delineate clearly at the
outset of project planning the respective responsibilities of the design-build
team members with regard to key project elements, such as budget, performance
objectives and schedule. Many of the
problems outlined here can be avoided by clear documentation of team roles at
the start of the proposal phase.
A. Failure to Assemble a Team of Subcontractors
and Suppliers Who Have Experience With Similar Projects.
Several
cases bear witness to the problems that can arise when a design-builder
involved in a large-scale, complex project fails to ensure that its team
members have sufficient experience to meet the project’s demands.
An Eighth Circuit case demonstrates
the importance of retaining a designer experienced in the relevant industry and
with projects of comparable scale. C.L.
Maddox, Inc., v. Benham Group, Inc.,[1]
dealt with a contract dispute arising out of a design-build project for the
extensive remodeling of a coal processing system at an electrical power plant
in Illinois. Maddox, the prime
contractor, subcontracted with Benham for design engineering services on the
project, including preparation of equipment lists and material quantity
estimates for use in preparing Maddox’s fixed price construction bid. Maddox contracted with Benham specifically
for an “in-depth study of equipment layouts, equipment sizing and to supply
necessary information and assistance for [Maddox] to prepare a final
construction cost (lump sum) for the project.”[2] At trial, a representative testified that
Maddox relied heavily on Benham’s estimates in preparing its bid, because
Benham possessed all of the design information.
Based on Benham’s estimates, Maddox signed a design-build contract for
$10 million.
As the Eighth Circuit understatedly
noted, “[t]he project did not go well.”[3] Among other things, Benham significantly
underestimated the amount of work required to complete the final design and
frequently failed to submit drawings in a timely fashion. Maddox ultimately sued Benham and another
subcontractor seeking $5 million for additional costs incurred on the project. Of Maddox’s claimed damages, $2.7 million
allegedly arose from errors by Benham in the information provided to Maddox for
use in bidding the project. The dispute
resulted in a five-week trial, and a jury award of $5 million. Through post-trial motions and appeal, the
defendants obtained a reduction in the damage award to the $2.7 million
attributable to erroneous bidding information that Benham supplied to Maddox.
At trial, expert testimony
demonstrated, among other things, that Benham had underestimated the project’s
engineering requirements; that Benham failed to schedule its work properly to
allow Maddox to meet the construction schedule; that Benham understaffed the
project; that Benham’s drawings demonstrated inadequate knowledge of materials
handling; that Benham underestimated the number of drawings that the project
would require; and that although Benham assumed the total engineering function
on the job, there was no evidence of experience by Benham in handling very
large material handling projects.[4] This last factor appears to have been key in
the project’s failure. The lesson
plainly implied from this case is that a designer with prior experience with
materials handling in the power industry, in addition to sufficient design
capabilities and staffing, could have avoided the drastic underestimates seen
in Benham’s work on the project.
The Maddox case is also
noteworthy for the fact that that Maddox ultimately had to bear over $2 million
in losses itself, although it had claimed that these damages also resulted from
failures by Benham and the other defendant.
The Eighth Circuit further reduced the jury’s damage award by an
additional $1.2 million claimed to have arisen from Benham’s “failure to guard
Maddox against Maddox’s own deficiencies.”
This claim was based on a contract provision stating that Benham “shall
keep [Maddox] informed of the progress and quality of the Work, and shall
endeavor to guard [Maddox] against defects and designs [sic] in the Work of
[Maddox].”[5] The court declined to accept Maddox’s
interpretation that this clause operated to shift to Benham the risk that
Maddox would not properly perform its own obligations under its contract with
the project owner.[6] The Eighth Circuit found that Benham had “no
duty under the contract to act as insurance against Maddox’s own carelessness.”[7] In addition, the Eighth Circuit affirmed the
trial court’s reduction of the jury’s damage award by approximately
$1.4 million because Maddox did not offer evidence that Maddox had been
damaged when the owner incurred expenses in these amounts to remedy defective
work resulting from the defendants’ breaches.
While these amounts may have been borne by bond sureties on the project,
the ultimate cost to Maddox was undoubtedly real. By the Eighth Circuit’s account, utilizing an
inexperienced design subcontractor turned this project into a total failure
from Maddox’s standpoint.
Another
case demonstrates that a material supplier’s level of know-how can also
drastically impact a design-build project’s success, particularly when the
prime contractor issues a purchase order before the design is complete. In Carolina Steel Corp. v. Palmetto Bridge
Constructors,[8] the
design-builder, Palmetto, entered a contract with the South Carolina Department
of Transportation for a complex bridge project over the Cooper River in
Charleston. The project design
ultimately included seismic requirements that differed from the DOT’s standard
designs. These issues cost Palmetto an
additional $1 million in a damages award in favor of its steel supplier at the
conclusion of the lawsuit.
Palmetto
contracted with Carolina Steel Corporation for the fabrication and supply of
all the steel required for the project.
Because the project was design-build, the final design was not complete
at the time Carolina Steel submitted its bid.
The bid drawings did not reflect that the project would eventually
incorporate a seismic design.[9] Rather, it appears that in bidding, Carolina
Steel assumed that the project would follow “standard SCDOT design.”[10]
Carolina
Steel bid to provide all of the required steel on the basis of one fixed unit
price per pound of steel. Because the
design was incomplete, the purchase order that Palmetto issued to Carolina
Steel allowed that a “[s]ubstantial deviation in design may necessitate a
change in cost which will be determined on a case by case basis.”[11]
When
the final construction drawings were released eight months after issuance of
the purchase order, the drawings showed that several interchange bridges had
increased in weight and complexity in order to comply with earthquake,
hurricane and collision criteria. These
design changes substantially increased the amount of steel required on the
project.
In
response to the changed design, Carolina Steel submitted several proposals to
simplify the design in an effort to reduce costs. However, Carolina Steel’s proposals were not
incorporated in the final design.
At
the conclusion of the project, Carolina Steel had been paid over $20 million
based on the agreed unit price, but had six outstanding claims for additional
payment totaling over $1.5 million.
After a bench trial, the court found in Carolina Steel’s favor on the
majority of its claims and awarded damages in excess of $1 million.[12] The contested issues varied, but included
disputes as to whether various changes constituted “substantial deviations”
from the as-bid drawings that justified a change in the unit price, as well as
disputes as to the weight calculation when the agreed-upon unit price
applied.
However,
all of the claims arose from the central assumption by Carolina Steel that the
design would follow standard SCDOT design and would not be augmented by the
ultimately-adopted seismic and related strengthening criteria. Carolina Steel demonstrates the risk a
prime contractor may incur when a major supplier makes a faulty assumption –
perhaps based on its own limited prior experiences - as to essential design
criteria and the design is incomplete at the time of bid. Seismic design criteria can significantly
increase material requirements. The
purchase order in this case was sufficiently open-ended to expose the prime
contractor to substantial increased material costs. The lesson learned? If significant design changes are still
possible that may drastically impact material quantities, it may be wise to
delay issuing a final purchase order for any major material supplier until
quantities can be accurately estimated, or alternatively to include a price
adjustment mechanism for critical materials in the contract with the owner in
order to pass increased costs upstream.
1. Failure to identify the disciplines
required to meet owner’s performance criteria.
Even
when design services are to be performed in-house by the design-builder,
problems arise when the level of design services provided are inadequate to
meet the owner’s criteria. Similarly,
failure to identify and provide key services necessary for the construction
phase may sound a project’s death-knell.
Both
problems surfaced in a recent Connecticut case.
Bakish v. Donnelly[13]
involved a high-end residential design-build project in Danbury,
Connecticut. The homeowners hired
Blaze-Design Build Group Inc. as design-builder for a substantial renovation
and expansion of a lakeshore property.
The agreement contemplated a phased project including demolition of an
existing structure, excavation, foundation and watertight shell
construction. Both parties acknowledged
the significant challenges that the site posed because of its lakeside location
and the presence of rock ledge.
After
demolition had taken place, it quickly became apparent that the design-builder
did not have the capabilities to perform the excavation needed to address the
site conditions. The homeowners chose to
subcontract out the excavation to a separate contractor. After this point, the project appears to have
gone rather quickly downhill. The design
proved to be deficient in several respects, including omitted roof trusses
required for structural reasons.
Construction slowed and ground to a halt. The homeowners sued for breach of contract,
claiming that the design-builder had overcharged for design services; that the
design was inadequate; that construction failed to conform to the homeowners’
requirements for quality, time and budget; and that construction was not completed.
The court ruled in favor of the
homeowners. The deficient design was a
key element of the case. The court noted
that the designer, one of the principals of the design-build entity, was not a
registered architect. Expert testimony
demonstrated that the design failed to comply with even basic design standards,
was structurally deficient, violated the building code, was inconsistent and
inadequate for construction purposes.
The homeowners had been forced to hire an architect to prepare a revised
design to allow construction to be completed.
Particularly in light of the fact
that the site’s challenges had been acknowledged by all parties from the
outset, the design-builder’s failure to come up with an adequate design was
fatal to the project. The design-builder
was required to pay damages to the homeowners for completion of the project and
related costs. Plainly, the case
demonstrates again that obtaining a design that conforms to the owner’s
performance criteria is key to the success of any design-build project.
B. Failure To Define Clearly the Roles and Responsibilities
in the Teaming and Proposal Phases.
1. Design-builder fails to define performance criteria for
subs, suppliers and designers in preparing proposals.
a.
Failing to
identify purpose of evaluation and input from subs and suppliers.
Failing
to spell out in the contract documents the intended use of input from
design-build team members, particularly designers, can lead to significant
disputes between the design-build team members.
CRS Sirrine, Inc. v. Dravo Corp.,[14]
involved a design-build project for a large and technically complex power plant
for the U.S. Navy at the Norfolk Naval Shipyard in Portsmouth, Virginia. Dravo and Sirrine formed a joint venture,
based on Dravo’s construction capabilities and Sirrine’s experience in the
design of similar projects. Fixed price
competitive bids were submitted on the basis of preliminary design and
engineering by the bidders. Detailed
design was done only after contract award.
The joint venture parties agreed
that Sirrine would prepare and submit the initial technical proposal, and if
the technical proposal was accepted, Dravo would assume primary responsibility
for preparing and submitting the bid. Sirrine
was responsible for supplying the technical information needed to prepare the
bid. The joint venture’s successful
competitive bid was in excess of $100 million.
The dispute arose because the plant
cost significantly more to build than the bid amount. Dravo incurred more than $30 million in
losses on the construction phase. Dravo
sued Sirrine seeking damages of $12.5 million, arguing (among other things)
that Sirrine had failed to provide sufficient, accurate information to Dravo
for use in the bid, had failed to design the project within budgeted
quantities, and had failed to give notice to Dravo that the bid quantities
would be exceeded. At trial, Dravo
recovered $5.5 million in damages.[15] On appeal, the case was remanded for
clarification of the damage amounts contained in the judgment.
The key to this dispute was the
letter agreement between the joint venture parties that allocated their
respective responsibilities for bidding and design. While providing that Sirrine was responsible
for supplying the technical information for Dravo to use in preparing its bid,
the letter agreement also stated that Sirrine would not guaranty the accuracy
of Dravo’s estimates used in preparing the bid.
Sirrine argued that the agreement unambiguously released it from any
responsibility for damages resulting from increases in construction material
quantities. On appeal, Sirrine claimed
that the trial court wrongly failed to enforce this provision.
The court of appeals affirmed the
trial court’s finding that the letter agreement between the parties was
ambiguous and did not intend to release Sirrine from all liability for quantity
overruns, if the overruns resulted from errors or omissions in Sirrine’s
pre-bid or post-bid design and engineering services.[16] While the agreement also contemplated that Dravo
would be responsible for any overruns resulting from its own bidding errors, in
the end it was unclear as to how responsibility for cost overruns would be
allocated between the parties. This
ambiguity was key to the dispute and appears to have prevented resolution of
the case prior to a costly trial and appeal.
It is possible that this dispute
could have been minimized if the exact allocation of responsibility for any
overruns had been spelled out in the letter agreement. Certainly the provision that apparently
protected Sirrine, the designer, from responsibility for overruns should have
been omitted or more clearly limited as to its application. Because the fixed-price bid had to be
submitted based only on the initial technical proposal and before final design
was completed, the key documents between the design and construction partners
should have more accurately dealt with the possibility of cost overruns, to the
extent that such overruns could not be recovered from the owner.
b.
Failing to specify design-builder’s reliance on input from
subcontractors or suppliers for pricing purposes and GMP proposals.
The
Sirrine case discussed above also plainly stands for the proposition
that the contract documents between construction and design partners need to
accurately and unambiguously state the design-builder’s reliance on design
information for its pricing purposes.
Otherwise, parties providing information for use in pricing will attempt
to escape liability and shift all responsibility for cost overruns to the
constructor.
c.
Failing to clearly delineate the extent and scope of design
responsibilities for subs and suppliers at the proposal stage.
When
the project requires design input from subcontractors or suppliers, the extent
and scope of these design responsibilities must be clearly defined and agreed
at the proposal stage. Failure to do so
can result in disputes such as the large-scale material cost overrun problem
seen in Maddox v. Benham, discussed above. In that case, there was no formal agreement
between the contractor, Maddox, and the designer, Benham, for the pre-proposal
design services. There was simply an
oral agreement, under which Benham would complete the drawings and
specifications necessary for the Maddox to prepare its bid, including equipment
list and quantity information.[17] Obviously, the deficiencies in these
documents were the source of the substantial overruns Maddox sustained on the
project, but the agreement lacked any definition as to Benham’s
responsibilities for errors or omissions in these pre-bid services. A formal agreement with the designer at the
proposal stage, including appropriate risk allocation provisions, should be a
baseline requirement.
d.
Failing to clearly obligate the subs, suppliers and design
professionals to the project performance requirements at the teaming and
proposal phase.
Similarly,
the design-builder should ensure that necessary subcontractors and other team
members are firmly obligated to participate in the project if their proposals
are used in the project bid. This issue
arose in Perini Building Co. v. Fisher, Albright & Masters, Inc.,[18]
a case involving a design-build project for a commercial headquarters in
Argonne, Illinois. Perini, the prime
contractor, solicited bids from trade contractors prior to submitting its
fixed-price bid to the owner. Fisher had
submitted a proposal for drywall and painting.
In submitting its proposal to the owner, Perini calculated that it would
ultimately change the design then under consideration, and would also go back
to subs to negotiate discounts and various changes in work scope.
After
being awarded the job, Perini approached Fisher to negotiate a different work
scope and the parties agreed on a revised scope and price of $1.9 million. Fisher submitted a written one-page proposal
reflecting the price and scope.
However,
it was the intent of both parties that a formal subcontract would follow,
including all necessary terms and conditions.
When Perini several months later provided its subcontract form to Fisher,
the parties encountered irreconcilable differences, particularly with regard to
terms for payment and termination.
Fisher ultimately notified Perini that it no longer wanted to negotiate
with Perini on the project and the parties’ communications came to a halt. Perini sued Fisher for breach of contract,
and on equitable theories.
Although
Fisher had already commenced work on the job, the court found that no contract
had been formed between the parties, because the formal agreement intended by
both sides was never reached, even after several months had elapsed. The court granted summary judgment dismissing
Perini’s breach of contract claim. The
court, however, denied both parties’ summary judgment motions on the issue of
promissory estoppel, finding that a jury could decide either way on whether
Perini had reasonably relied on Fisher’s oral agreement as to price and scope
reached after the bid date.
The
Perini case demonstrates that a design-builder must reach enforceable
agreements with team members whose bids are key to the project. Design-build may differ in this respect from
a traditional competitive bid situation, where the general’s reliance on a
subcontractor’s proposal in its submitting the general’s winning bid will
generally create a binding promissory estoppel.
As in Perini, if the design or other requirements are to be
changed after acceptance of the bid, there may be no enforceable obligation on
the sub’s part, unless a separate independent agreement is negotiated and
signed. To avoid being left without a
key subcontractor when the project is already well underway, the design-builder
should obtain agreements with subcontractors as soon as scope and price can be
agreed.
2. Design-builder fails to recognize and
provide for professional licensing compliance for design
participants/contributors.
a. Failing
to recognize licensure requirements applicable to the design-builder.
The potentially devastating
consequences of failure to obtain the required licensure for designers working
on design-build projects are now well-known.
Courts have denied payment to design-builders who render design services
without first obtaining the licensure required in the jurisdiction, and may
require disgorgement of fees wrongfully obtained. For example, in Food Management, Inc. v. Blue Ribbon Beef, Inc.,[19] a
turnkey contractor’s act in gathering data within State of Iowa while
fulfilling a contract whereby it was to design, supervise construction, and
initially operate a meat packing plant constituted the unauthorized practice of
architecture. The court severed the
contract and only allowed enforcement of the non-architectural portions. Design-builders need to remain vigilant regarding
licensure requirements – or design-build prohibitions - that may be triggered
by their activities in any jurisdiction and ensure that they are in compliance
before entering any contracts or beginning work.
b. Failing to
coordinate licensure requirements for lead designer, suppliers, and subs with
design responsibility.
The Bakish case discussed
above[20]
illustrates the problems that can follow from the design-builder’s failure to
ensure that the designer is properly licensed and in compliance with other
regulatory requirements. As noted, the
designer, a principal of the design-build firm, was not a registered
architect. Moreover, the design-build
entity had failed to comply with Connecticut’s Home Improvement Contractors Act
(HIA). The parties’ contract failed to
include certain provisions required under HIA.
The court further noted that the principals were ignorant of HIA’s
requirements. Their failure to comply
with HIA also constituted a per se
violation of Connecticut’s Unfair Trade Practices Act. The defendants’ HIA violation was factor the
court considered in denying their counterclaims for setoff for sums allegedly
owed.[21]
C. Design-Builder’s Failure to Adequately Apprise Design
Participants of Their Responsibility for Meeting Contract Performance
Specifications.
1. Failure to Convey Purpose and Use for Conceptual Estimating
and Pricing; Quantity estimates and systems or process selection (for pricing
by team)
Design-builders
should ensure that the intended purpose and use for information supplied at the
proposal phase is clearly stated in the contract documents with designers. Failure to do so can result in the designer’s
attempts to evade responsibility when the design and/or material estimates
later prove to be woefully inadequate, as seen in the Maddox and Sirrine cases
discussed above. Without a clear written
communication as to the intended use of the designer’s work product, holding
the designer accountable may be unnecessarily difficult. As a baseline requirement, the purpose and
use of estimates and pre-proposal design as a basis for bidding should be
clearly enunciated in a formal written agreement, along with allocation of
risks as between the constructor and designer for any errors or omissions in
this material.
2. Clearly conveying that subs are
responsible for performance of the system in the context of overall project
performance criteria.
Similarly, the design-builder may
encounter problems if the contract documents fail to convey that subcontractors
are responsible not only for design but also ultimate performance of the system
and compliance with the project’s performance criteria. The Maddox
case provides a clear illustration of this point. The court expressly noted that the omissions
of the designer, Benham, included a failure to properly define the project’s
objectives.[22] However, the basis of the designer’s defense
was that it was protected from any liability arising from defects in the
pre-bid estimates that it furnished.
Benham argued, albeit unsuccessfully, that the parties’ oral agreement
for its pre-bid services was unenforceable under the parole evidence rule; and
further that it never warranted that the bidding information was accurate.[23] These arguments were ultimately
unsuccessful. However, the court did
agree with Benham’s contention that it had no obligation to protect Maddox from
Maddox’s own deficiencies during the construction phase.[24] If written contract documents had clearly
spelled out that Benham’s responsibility included achieving successful
compliance with the owner’s project performance criteria, these issues could
have been avoided or dealt with in a more satisfactory manner.
D. Design-Builder’s Failure to Recognize the Extent of
Diffused Design and Account for All Required Design Input.
1. Failure to coordinate design of systems.
Problems may arise on projects where
multiple subcontractors or suppliers are required to supply design input, but
the various design contributions are not carefully coordinated. In the Maddox
case, the problems at the coal processing system were not limited to
deficiencies in Benham’s bidding information.
Maddox also sued a separate subcontractor, Dynalogic, who designed and
supplied the computer control system for the coal processor. The owner ultimately determined that
Dynalogic “never produced a product [that was] dependable,” and finally
replaced it with an entirely new computer system at a cost of over $300,000.[25] The description of the project’s course
demonstrates that the software Dynalogic supplied never operated correctly and
suggests that Maddox failed to control coordination of Dynalogic’s system
design with Benham’s design input.
2. Failure to convey and account for scheduling and schedule
impact of design phase including design review and approval by design builder
and owner of all design contributors (in the proposal phase).
Contracts for large-scale build
projects can impose severe liquidated damages provisions in the event that the
project fails to meet the owner’s required completion date. A key source of
delay in the design-build context can be failure to obtain a complete, approved
design in a timely manner in order to allow construction to proceed on
schedule. Several of the cases discussed
demonstrate the consequences of delay in design completion. For example, in Sirrine, the court awarded over $1.5 million in damages against
the designer because of delays attributed to the designer’s deficiencies.[26] The court found that 91 days of delay were
caused by the designer’s failure to give timely notice of quantity growth, late
issuance of released for construction drawings, and increased material
quantities. An additional 102 delay days
were caused by plain design error.[27]
There was no contractual method
specified to account for negative scheduling impacts resulting from designer
error. Design-builders should consider
whether such a provision is necessary to avoid a protracted dispute such as
that seen in Sirrine.
In
addition, cases demonstrate that the time needed to obtain final owner review
and approval of the design documents can be significantly underestimated. In Maddox,
the litany of Benham’s failures noted by the court included failure to properly
estimate the project’s engineering requirements; failure to schedule its design
work in order to allow the construction schedule to be met; underestimating the
number of drawings needed; and understaffing.
Some of the delays in finalizing the design were due to continued
changes by the owner and delays by Maddox in submitting vendor-prepared
drawings to Benham for review.[28] The case teaches that when multiple parties
are involved in the design preparation and review process, adequate time must
be included in the schedule agreed to by the design-builder.
E. Design-Builder’s
Failure to Plan for Code Compliance.
1. Competitive
Bidding
Design build participants should be aware of the
potential hazards surrounding design-build contract procurement on public
projects. Design-build contract awards
on public projects are particularly susceptible to challenge by disappointed
bidders and others for alleged violation of competitive bidding
requirements. For example, C&C/Manhattan v. Gov’t of the
Virgin Islands[29]
was a bid protest decided in 1999 regarding contracts for the design and
construction of three government facilities, including a prison and a jail, in
the Virgin Islands. The unsuccessful
bidder, C&C, sought and obtained an injunction preventing the government
from proceeding with the prison contract awarded to C&C’s competitor, Hyde
Park. The basis for C&C’s challenge
was noncompliance with Virgin Islands’ competitive bidding laws.
In
order to abate prison overcrowding, the government had adopted an expedited
process to hire a single contractor to design and construct the
facilities. The expedited process
essentially consisted of an RFP and negotiated agreement. C&C argued that it was the “lowest
responsive bid proposer,” and that under the Virgin Islands’ competitive
bidding laws, it should therefore have been awarded the contract.[30] The government rejected the protest on the
grounds that competitive bidding laws did not apply to the RFP and negotiation
process that it had adopted.
In
granting the injunction, the court noted the general rule that the Virgin
Islands government was required to competitively bid all construction
contracts. In adopting the RPF and
negotiation procurement process, the government relied on the “professional
services” exception to the competitive bidding requirement.[31] The exception provided that contracts for
professional services could be made without competitive bidding, provided that
“competitive negotiation” was used where practicable. The government argued that the design-build
contract let to Hyde Park was a professional services contract and thus within
the competitive bidding exception.
The
court rejected the government’s position, finding that the prison contract was
not a contract where the construction services were “merely incidental” to
exempt professional services. Rather,
the “bulk of the work” was not of a professional nature, but was construction
work. The court noted the lack of any
specific statutory authority allowing the Virgin Islands to let design-build
contracts on public projects, in contrast with the design-build procurement
method expressly authorized by federal regulations.[32]
The
result in C&C should not come as
a great surprise today, as it is generally acknowledged that a public entity
needs specific statutory authorization in order to utilize design-build
contract procurement if competitive bidding would otherwise apply to
construction contracts in the relevant jurisdiction. However, it is worth noting that design-build
projects continue to be the subject of challenges based on alleged violation of
competitive bidding regulations.[33] In a case decided in 2003, Sloan v. Greenville Cty.,[34]
the appellate court upheld the use of design-build procurement on two road
improvement projects, but threw out the design-build procurement process that
the same county used on a forensic lab project, because it failed “to provide
any reasoned basis for the decision to use design-build source selection.” Although the county’s ordinances permitted it
to use design-build, the court found that the county had failed to meet its own
standards for making a determination that design-build was appropriate in this
particular instance.[35] Practitioners and design-builders need to
keep on top of regulations and statutes authorizing design-build on public
projects, and to ensure that procedures are strictly followed in order to avoid
challenges to the legitimacy of public design-build contracts.
2. Building Code Compliance
Design-builder s will of course be subject to the
same liability for failure to comply with applicable building codes as other
contractors. For example, Bakish v.
Donnelly,[36]
discussed above, demonstrates the problems that resulted when one of the
design-build principals herself prepared a design that violated the building
code. In the design-build context,
however, the team leader will need to ensure that checks are in place to
monitor code compliance by subcontractors and design consultants.
a. Failure to monitor code compliance by
subs and design consultants.
The Carolina Steel case indicates the types of problems that can occur
when a design-builder fails to establish a protocol to ensure that
subcontractors understand and are complying with applicable codes or standards
during the proposal phase.[37] The seismic and collision design criteria
that ultimately applied to the steel for this complex bridge project led to
massive increases in material costs that eventually cost the design-builder an
additional $1 million on this job.
Subcontractor assumptions regarding applicable codes or standards should
be verified before bids are submitted.
Similarly, the design-builder should establish a protocol for ensuring
that consultants or subcontractors tasked with design responsibilities are
aware of all applicable codes, including any special requirements for the
specific project at issue. By closely
monitoring code compliance during the proposal and design phases, potentially
expensive problems can be averted.
Note however, that code compliance
alone may not be a complete defense to a claim of negligence against a
design-builder. In Williams v. Melby,[38]
a design-builder (among others) was sued after an apartment tenant fell through
a third-story bedroom window and sustained severe injury. The plaintiffs claimed that even though it
complied with the applicable code, the window’s design was negligent and had
caused the injury. The court held that
code compliance does not ipso facto
preclude a finding of negligence. The
court noted that the builder had chosen the design and approved the plan and
was therefore “responsible to avoid unreasonable risks created in the final
product.”[39]
fb.us.1651049.01
[1]
88 F.3d 592 (8th Cir. 1996).
[2] Id.
at 596.
[3]
Id. at 595.
[4]
Id. at 597.
[5] 88
F.3d at 602.
[6] Id.
[7] Id.
[8] 444
F.Supp.2d 577 (D. S.C. 2006).
[9] Id.
at 580.
[10] Id.
[11] Id.
[12]
Analysis of the claims
further reveals that in several instances, Carolina Steel provided pricing of
the changed items to Palmetto before commencing manufacture and that Palmetto
apparently approved the increased pricing.
Not surprisingly, the court found that Palmetto’s apparent approval
rendered those claims valid. See, e.g., 444 F.Supp.2d at 581-82.
[13] 2004
WL 335006 (Conn. Super. Jan. 26, 2004).
[14] 445
S.E. 2d 782 (Ga. App. 1994).
[15] Id. at 784.
[16] Id. at 787.
[17] Maddox, 88 F.3d 592, 597.
[18] 1998
WL 100274 (N.D. Ill. Feb. 23, 1998).
[19] 413
F.2d 716 (8th Cir. 1969).
[20] 2004
WL 335006 (Conn. Super. Jan. 26, 2004).
[21] Id.
at *4.
[22] Id. at 597.
[23] Maddox, 88 F.3d at 600.
[24] Id.
[25] Id. at 597.
[26] Sirrine, 445 S.E.2d 782, 785.
[27] Id.
[28] Maddox, 88 F.3d at 598.
[29] 1999
WL 117765 (Terr. V.I. Feb. 12, 1999).
[30] Id. at *4.
[31] Id.
at *6.
[32] Id.
at *9.
[33] See, e.g., Sloan v. Greenville Cty., 590
S.E.2d 338 (S.C. App. 2003) (taxpayer suit challenging award of three
design-build public works projects for alleged violation of county procurement
ordinances).