American Bar Association

Forum on the Construction Industry / TIPS Fidelity & Surety

Law Committee

 

_______________________________________________________________

 

 

 

 

 

Use of Bridging Consultants in Design-Build RelationshipsBridging

 

 

 

 

 

G. William Quatman, FAIA, Esq.

Shughart Thomson & Kilroy, P.C.

Kansas City, Missouri

 

 

L. Tyrone Holt, Esq.

L. Tyrone Holt, Esq. The Holt Group, LLC

Denver, Colorado

 

 

 

 

January 25, 2007

The Westin St. Francis, San Francisco, CA

 

 

 

 

 

 

__________________________________________________________________

 

© 2007 American Bar Association


 

I. History and Introduction.

 

A. What Is Bridging?

 

On most design-build projects, the architect or engineer works eithereither works in-house for the contractor, or serves in a subservient role as a subcontractor. In still other cases, the design professional leads the design-build team by holding the prime contract or acts as a joint venture partner. With any of these forms of delivery, the project owner does not have what it considers an “independent” design professional watching out for the owner’s interests. Designers and contractors complain that in a design-build competition, the cost of preparing designs sufficient to submit cost proposals often prevents otherwise qualified teams from participating. . To solve both problems some owners (especially in the public sector) retain an independent design consultant to prepare a preliminary design, then prepare outline specifications, assist with the RPF and selection process, and even stay on board during the construction phase to review pay applications, inspect the work and certify the completion date. . “Bridging” is the name given to this process. A graphic depiction of bridging is shown in figure A, below.

As shown below, the owner hires a design consultant (the “Design Criteria Consultant”) to) to prepare design documents, usually to a level of no more than 30% complete. Those schematic design documents are then used to obtain competitive proposals from design-build teams. The successful team will include architects and engineers who will complete the technical drawings with the remaining 70% of information needed for construction. Since the design is often already laid out by the owner’s consultant, some refer to the successor’s role as “Draw-Build,” in that the design is already set and all that is left for the design-build team is to “draw it.” The Design-Build Institute of America (DBIA) sometimes refers to this method of delivery as “Design/Design-Build” or two other equally awkward names “Design-Build/Bid” and “Design-Draw/Build”.[1] Still others call the role of the owner’s design consultant “A/E-1.”

In the most common forms of bridging, the owner’s design consultant remains as the owner’s representative to provide limited construction administration services, including final inspections and close out of the project, acting in the traditional role of the architect or engineer. The owner’s consultant may function as a neutral in resolving disputes and in passing judgment on the quality of work.

 

Figure A. The Bridging Concept

 

1. Origins and Brief History

 

The term “bridging” was conceived by George Heery, FAIA, formerly of Heery International, now a principal of The Brookwood Group in Atlanta, Georgia. But the concept of one design professional completing a design started by another is not new and has ancient roots. . Bridging goes back to the days of pharaohs and pyramids, when due to a shorter human life span and the decades it took to build the great Egyptian and Mayan pyramids, designs started by one person were completed by another by necessity. . Centuries later, with the Gothic and Italian Renaissance cathedrals, it was expected that the original designer would not be the same one to oversee the project’s completion for the same reason. Italian Renaissance architect Leon Battista Alberti remarked in the 15th Century that, “The brevity of human life and the scale of the work ensure that scarcely any large building is ever completed by the same man as begins it.” Paying homage to the original designer’s intent, Alberti continued, “I feel that the original intentions of the author, the product of mature reflection, must be upheld.” [2]

A good example of this is the great red-tiled cathedral in Florence, Santa Maria del Fiore, whose original design was the combined work of architect Giovanni di Lapo Ghini and a competing master mason, Neri di Fioravanti. The two designers built huge scale models of their building designs in 1366. The Fioravanti design was chosen in 1367, with its unprecedented 143 foot wide dome. [3] His model alone was 15 feet high and 30 feet long. The great cathedral took decades to construct and each year the cathedral’s architects and wardens were required to place their hands on a copy of the Bible and swear an oath that they would build the church exactly as Fioravanti’s model portrayed it.[4] The project was later completed by yet another master-builder, Fillipo Brunelleschi, whose model won the competition in 1418 to complete the cupola (or dome) and a later competition in 1436 for the lantern on top of the dome. So while many credit Brunelleschi as the “architect of record” for the Florence Cathedral, it was Fioravanti whose elaborate set of “bridging” documents – his huge model - outlined the overall design for the structure and dome, while Brunelleschi merely engineered and finished the great dome as a successor architect.

In modern-day design-build, the role of the owner’s consultant is written into the laws of many states. The AIA, EJCDC and DBIA all publish form contracts to be used in hiring an owner’s consultant to represent and assist the owner, including the preparation of a preliminary design. [5] The concept has its fans and critics, like anything else.

I. The Basics

 

A. What is Bridging?

 

1. Origins2

. Industry Definitions

 

The AIA and AGC defined bridging in a joint 1995 publication like this:

 

“Bridging is a hybrid of the traditional design-bid-build process and design-build. An owner selects an AE to develop a project design through design development (approximately 30 percent - 50 percent of the design work), and prepares scope of work documents which form the basis for competitive selection of the project delivery team. The AE specifies the project’s functional and aesthetic requirements but leaves the details of construction technology up to the contractor. Construction technology is specified with performance specifications. The project delivery team then has single-point responsibility for final design and constructing the project.”[6]

 

3. The Canadian View

 

The concept of bridging has crept across the border into Canada. The Canadian Design-Build Institute (CDBI) defines “Bridging Consultant” in its Practice Manual as, “An individual or firm employed or engaged by an owner to develop a design to an advanced stage whereby the design-builder’s role is reduced to completing the construction documents and construction (see Draw-Build).”[7] The CDBI Practice Manual defines “Bridging” as, “A form of design-build delivery whereby the owner enters sequentially into two separate contracts. The first contract is with a Bridging Consultant who prepares preliminary and developed designs. The second is with a draw-builder who completes (and assumes responsibility for the design prepared by the Bridging Consultant) the construction documents and builds and delivers the project.”[8]

The CDBI plainly sees the role of the design-build contractor as merely drawing up the design prepared by the Bridging Consultant, calling this form of project delivery “Draw-Build,” while assuming full liability for the design prepared by the Bridging Consultant.

4. Design Criteria Consultants

 

States that have fully developed design-build statutes or regulations often write the role of the bridge firm into the law. Florida was the first to do so with its “Consultants’ Competitive Negotiation Act.” [9] Under the Florida Act, a “design criteria professional” is selected to prepare a “design criteria package” used toused to furnish sufficient information to permit designpermit design-build firmsbuild firms to prepare a bid or a response to a Request for Proposal. The design criteria package is to include:

“performance-based criteria for the public construction project, including the legal description of the site, survey information concerning the site, interior space requirements, material quality standards, schematic layouts and conceptual design criteria of the project, cost or budget estimates, design and construction schedules, site development requirements, provisions for utilities, stormwater retention and disposal, and parking requirements applicable to the projectstormwater.”

 

Under the Florida Act, the design criteria professional must be abe a firm that has a current certificate of registration to practice architecture or engineering. The firm is selected using a qualifications-based process similarprocess similar to the procedures used to hire design professionals for state work. In determining whether a firm is qualified, the agency is to consider such factors as the ability of professional personnel; whether a firm is a certified minoritycertified minority business enterprise; past performance; willingness to meet time and budget requirements; location; recent, current, and projected workloads of the firms; and the volume of work previously awarded to each firm by the agency, with the object of effecting an equitable distribution of contracts among qualified firms. Some other states that have written the role of design criteria consultant into their procurement laws are Nebraska, South Dakota and West Virginia (all of which call this role “performance-criteria developercriteria developer”). [10]

5. Mini-Bridging

 

A variation used by some design firms who lead design-build projects has been called “mini-bridging.” In this model, the design-builder hires trusted engineering consultants to prepare design criteria and performance specifications. Those preliminary designs are then given to trade subcontractors who act as design-build subcontractors for their respective portions of the project, e.g. mechanical, electrical or even structural components. The appeal of this model is that the design-builder can select trusted engineering consultants to prepare design criteria that will meet the project needs. This gives a comfort level when working with design-build trade subcontractors in whom the design-builder does not have complete confidence. The trade subcontractors must prepare designs that meet the specified performance criteria.

B. Pros and Cons of Bridging?

 

1. Con’s of Bridging. The detractors of bridging discourages this method of procurement, stating that it,it eliminates many of the advantages inherent in true design-build. For example, DBIA’s primary argument against bridging is that the real advantages of design-build are lost when the design is merely handed to the team at a 30% level of completion. Among DBIA’s criticisms of bridging are:

1. That this method precludes the design-build team from any significant creativity and innovation, since basic solutions and concepts are determined before the design-build team begins.

 

2. Work performed in the first phase determines many of the design and functional aspects of the project for which the phase two team has to take responsibility (and liability), without any real input, leading for greater potential for disputes.

 

3. True design-build permits fast-track construction with the ability to procure long lead time items and begin field operations well before a project is at the 35% point of design.

 

When more than 30% of the design is provided in the RFP, the selection of the design-build team tends to be more price oriented since the design is already set. In those cases, there is often less emphasis on qualifications-based selection. DBIA urges selection of design-build teams based on a combination of qualifications and price, but feels that under “bridging” or “design/design-build” the selection is based solely on the basis of low price. Case studies of actual public sector projects would show otherwise, since bridging is regularly used in public procurement, yet qualifications of the design team remain a large portion of the selection criteria.

The level of design done by a bridging consultant varies. In the best uses of bridging, there is a great amount of design left up to the design-builder, who can be innovative in developing the design. When all that is left is to draw up the plans, however, the real value of design-build is lost. The level of completeness of bridging documents is an open debate and is often project-driven. One study by the New York State Department of Transportation in September 2002 reported the following ranges of designs included in procurement packages for highway and other project types: [11]

 

5% to 15% Alameda Corridor Transportation Authority

10% Florida DOT

10% to 20% Arizona DOT

10% to 40% Ohio DOT

15% Utah DOT

20% Atlantic City/Brigantine Connector (New Jersey DOT)

30% Utah Transit Authority (light rail project)

30% to 40% Washington State DOT

35% initially NAVFAC (NAVFAC (now ranges 15% to 35% depending on project complexity)

35% Transportation Corridor Agencies (Eastern)

35% Transportation Corridor Agencies (Glenwood)

35% Transportation Corridor Agencies (San Joaquin)

 

2. Pro’s of Bridging. On the “Pro” side, corporate owners have been downsizing in-house construction staffs and outsourcing more of those functions. With design-build, where the project’s program and design-build selection are important to success, owners need help because they have more responsibility for defining and procuring than in traditional construction where an A/E firm traditionally helps with programming and contractor selection. This presents opportunities for a new type of owner-consultant, such as program managers, and even new roles for traditional design or construction management firms.

Where modest stipends are awarded to the unsuccessful design-build teams, most would agree that the amount received does not come anywhere near covering the cost of the actual design competition. If five firms are short-listed, with only one winning the full design-build contract, the four unsuccessful teams can invest substantial sums. Only the larger firms can play that game on a regular basis and write off the uncompensated design effort. However, with bridging the teams do not have to incur a costly design fee just to compete, and can use the preliminary design prepared by the bridging firm. This entices more qualified firms, more often, to participate when there is no expensive design competition.

Owners are used to having an architect to discuss the project with, to advise them and to “keep an eye on the contractor”. Design-build without a bridge consultant requires a great deal of trust. Some owners are just not ready for that level of trust and a bridge consultant helps make the transition to design-build.

3. Bridging As A Target Market. Bridging is a target market for some design firms. The CEO of one large A/E firm in Virginia said in 1999 that his firm’s main focus is to be an “A/E-1”, handling conceptual design and then acting as the owner’s agent supervising the design-build team.[12] With firms targeting this role for their business niche, expect more competition. Firms will begin to compete on who is the most qualified “bridge” firm.

While fees for “bridge” architects are generally less than for traditional full-scope services, there is an attraction toward this service for at least three reasons. First, most architects will agree that the “fun” part of architecture is the design phase. Construction documents and specifications, the technical side of design, preparing “working drawings” is the less glamorous aspect. Bridge architects get to do concept designs, the way architects did in studio in college, leaving the remaining sticky, technical drawings and detailed specifications to the design-build team to develop. Second, the bridge architect retains a close relation to the owner, preserving the role of agent, advisor and trust that is enjoyed on traditional project delivery. Last, there is less risk for the bridge firm. Insurance statistics show that the majority of claims against A/E firms are for design errors or omissions. With the bridge firm doing only a 30% or so set of schematic or design development drawings, which are normally not even sealed, it is expected that the design-build team will prepare the final technical details used for construction and seal those documents. If there is a design error or omission in the drawings or specifications, liability will most likely fall on the design-build team’s architect or engineer who prepared those documents, not on the bridge firm.

 

C. Industry Views on Bridging

 

Up until 2005, the AIA’s official Position Statement on design-build and bridging recommended that when public agencies use design-build, they should put out a detailed RFP with “project specific comprehensive scope of work documents prepared by licensed architects and other qualified professionals who are retained for the duration of the project.” The AIA also recommended that the design-build proposals are evaluated by a jury of qualified professionals, “including those licensed professionals who prepared the scope of work documents”. AIA recommended that the design-build entity be required to retain and use the design architect of record “throughout the duration of the project to maintain design integrity, functional and technical responsiveness, and to conduct on-site construction observation.” This is, of course, intended to make sure that the contractor does not hire an architect only to prepare construction documents, with no role during constructionduring construction. The AIA’s official Board Position on alternative delivery was revised in 2005 and no longer takes a position on bridging.

2. Industry Definitions

3. Canada, elsewhere

 

B. Owners: Pros and Cons Like it.

 

C. “Mini-Bridging” Defined and Recommended Applications

 

D. Industry Views on “Bridging”

 

II. Legal Issues in Bridging.II.

 

A. Selection Laws

 

In those states with laws governing the selection of a design-criteria consultant, it is stated that the selection shall be on qualifications, just like when hiring an architect or engineer. Once chosen to be the owner’s consultant, however, many states bar the owner’s consultant from serving on a design-build team for that same project due to either a conflict of interest, or an unfair advantage to a design-build team who snatches up the owner’s confidential advisor.

Several states have laws that prohibit an architect or engineer from bidding on plans they prepare.[13] South Carolina law bars architects and engineers who perform design services from performing any work on the same project as a contractor, either directly or through a business in which the architect or his firm has “greater than a five percent interest”.[14] The intent of such laws is to prevent an unfair competitive advantage to the firm most familiar with the design. It would certainly defeat the purpose of having an “independent” architect/engineer if the bridge firm could prepare the design criteria package and then link up with one of the design-build teams competing for the project. The better approach is to bar the bridge firm from participating on any of the design-build teams.

Florida’s “Consultants’ Competitive Negotiation Act”, Fla. Stat. § 287.055, makes it clear that, “A design criteria professional who has been selected to prepare the design criteria package is not eligible to render services under a design-build contract executed pursuant to the design criteria package.” Likewise, South Dakota procurement law states that, “The performance criteria developer may not submit a proposal to enter into the design-build contract and the design-builder may not delegate or contract services under the design-build contract to the performance criteria developer.” [15] West Virginia says the performance criteria developer is “disqualified” from submitting a proposal and no design-builder may delegate services to the performance criteria developer. [16]

At least one Federal case has ruled that in this situation, the bridge firm cannot be part of a contractor’s design-build team.[17] The court ruled that Federal Acquisition Regulations (FAR) barred such participation and that with the bridging consultant’s participation, that team would have an unfair competitive advantage and an “organizational conflict of interest”. The case hinged, in part, on a Federal regulation, FAR part 9.505-2. That regulation stated that, “If a contractor prepares, or assists in preparing, a work statement to be used in competitively acquiring a system or services -- or provides material leading directly, predictably, and without delay to such a work statement -- that contractor may not supply the system, major components of the system or the services [with certain exceptions]”.

B. Conflicts of Interest

 

The current AIA Code states:

 

“E.S. 3.2 Conflict of Interest: Members should avoid conflicts of interest in their professional practices and fully disclose all unavoidable conflicts as they arise.

 

Rule 3.201 A Member shall not render professional services if the Member’s professional judgment could be affected by responsibilities to another project or person, or by the Member’s own interests, unless all those who rely on the Member’s judgment consent after full disclosure.”

 

Refer also to the NSPE Code of Ethics for Engineers, Rule II. 4.a (July 1996) which requires disclosure of all known or potential conflicts of interest that “could influence or appear to influence” the engineer’s judgment. Conflicts of interest are the most common ethical issue in design-build, so much so that federal regulations discuss this topic. The regulations published by the Department of Transportation’s Federal Highway Administration in December 2002, (67 Fed. Reg. 75902), show that significant thought was given to the issue of organizational conflicts of interest. The final rules state in 23 C.F.R. §§ 636.116 to 636.118 that policies on conflicts of interest should be stated in the RFQ or RFP, including that consultants who assist the owner in preparing the RFP will not be allowed to participate on a design-build team, unless involvement was at a “low level”.

FAR 9.502 states that an “organizational conflict of interest” may result when there are factors which create “an actual or potential conflict of interest on an instant contract, or when the nature of the work to be performed on the instant contract creates an actual or potential conflict of interest on a future acquisition.”[18] Participating on a competing team may give that team an advantage in terms of qualifications since no other team could match the level of familiarity that the developer of the scope of work would have with the project. It would also effectively prohibit the owner from using that same design consultant for construction administration services during construction.

C. Spearin Doctrine and Bridging

 

Bridging adds a new twist to the proper role of the Spearin[19] doctrine in resolving the dispute. As the educated construction lawyer knows, the Spearin doctrine holds, generally, that when the owner furnishes detailed specifications to a contractor, the owner is deemed to impliedly warrant that those plans and specifications are accurate and suitable for their intended use. The Spearin case held that, “if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications.” [20] How does bridging change this doctrine? The answer depends on the level of design detail provided by the owner’s consultant, and the amount of design discretion given to the design-build team.

As noted by the Veterans Administration Board of Contract Appeals in one case:

 

A properly written and administered design build contract transfers the risk of design and sufficiencies from the VA to the design builder. The owner is shielded when the design results in cost over-runs or does not work. M.A. Mortenson, ASBCA No. 39978, 93-3BCA, ¶ 26, 189. . . .Specifications included in a design-build contract, however, to the extent that specific requirements, quantities, and sizes are set forth in the specifications, place the risk of design deficiencies on the owner. [21]

 

When the owner elects to substitute its discretion for that of the design-builder by providing detailed specifications via its bridging consultant, the owner should expect to carry the risk that comes with that substituted discretion, under traditional Spearin concepts. If the owner, in its effort to provide the design-builder a better idea of exactly what the owner seeks from the scope of work, provides erroneous or faulty information, the owner can be expected to bear liability under an implied warranty as with “traditional” project delivery.

D. Performance vs. Prescriptive Specs

 

In the 2002 New York DOT study, a number of state agencies surveyed indicated their preference for performance specifications where possible on design-build projects, but almost all of the agencies relied on prescriptive specifications for significant portions of the project. [22] This can create a mixed bag of legal issues to sort out on public design-build projects when both types of specifications are included in the bridging documents.

Performance Specifications describe an end result, an objective or standard to be achieved, and leave the determination of how to reach the result to the contractor. [23] By contrast, Design or Prescriptive Specifications set forth in detail the materials to be employed and the manner in which the work is to be performed, and absent special circumstance, the contractor is required to follow them as one would a road map and without deviation.[24] It is not uncommon for a contract to contain both design and performance characteristics, and certainly one can find numerous government contracts exhibiting both performance and design specifications. Therefore, some forethought needs to be given into the level of detail contained in a set of bridging documents. The more detail and prescription given to the design-build team by the owner, the more likely the owner will be deemed to warrant the adequacy of its documents.

E. Ownership and Copyrights

 

The bridging consultant certainly is aware that another design professional will use its preliminary design to complete the project. Therefore, it is without saying that a firm serving as owner’s design consultant must authorize the successful design-build team to copy and use its design. However, the bridging consultant may wish to restrict the use of the design to this one and only project, so that a successful design could be used again under control of the bridging professional.

AIA’s B142, Owner-Consultant Agreement (2004 edition), says in Paragraph 3.2.1 that, “Drawings, specifications, and other documents, including those in electronic form, prepared by the Consultant and its sub-consultants are Instruments of Service for use solely with respect to the Project. The Consultant and its sub-consultants shall be deemed the authors and owners of their respective Instruments of Service and shall retain all common law, statutory and other reserved rights, including copyrights.” The consultant grants the owner only a license to reproduce and use the documents in connection with the one Project, “including the Project's further development by the Owner and others retained by the Owner for such purposes, including the Design-Builder and the Design-Builder’s design professionals.” The license extends specifically to the design-builder and it design professionals.

F. Who Is The A/E of Record?

 

It will be interesting to see how design professionals handle the credit for projects in which one firm does preliminary design and another serves as the design-build team’s architect. Many of the AIA ethical complaints relate to one firm not giving proper credit to another firm when both play a role in the project. This comes up in awards competitions, in marketing brochures and in subsequent head-to-head competition and interviews. Two firms showing the same project in their qualification statement and brochures will confuse owners and hurt credibility. There is also the conflict as to who is the “architect of record” or “engineer of record” for the project. These labels, which have no legal meaning nor definition in standard contracts, often cause confusion when multiple firms are involved. Who is the true project “architect” on a project in which one firm does the bridge package and another firm does the remaining 70% or so of the design work?

The AIA’s ethical Rule 4.201 requires members to “accurately state the scope and nature of their responsibilities in connection with work for which they are claiming credit.” The official commentary to this Rule says that the intent is to prevent members from claiming credit for work they did not do and “denying other participants in a project their proper share of credit.” Seven of the AIA’s ethics decisions between 1987 and 1992 dealt with the giving or taking of credit for work. With bridging injecting two design firms into a project, we can expect more ethics complaints unless firms come up with a way to credit a competing firm with their role as either bridge architect or project architect or some other terminology.

Documentation:

A. AIA, DBIA, AGC, others

 

B. Custom Documents

 

III. State Laws on Design Criteria Consultants.

A. Similarities

B. Differences

 

IV. How to Select Bridging Firms.

A. Selection Criteria; Procedures

B. Who Can Qualify?

 

V. Negotiating Bridging Arrangement

 

A. Owner’s Perspective

 

B. Design Perspectives

 

C. Construction Perspective

 

D. Recommended Practices and Pointers Designed to Achieve Successful Projects.

 

1. When Bridging Goes Too Far.

 

2. Amount of Information Provided

 

VI. Liability of the Bridging Firm.

A. Liability of Owner; Spearin Doctine

 

B. Insurance Coverage and Risk Allocation

 

VII. Bridge Firms Participation on Design-Build Teams.

 

A. Unfair Competitive Advantage

B. Projects That Change Delivery Mode

C. State and Federal Laws

D. Case Law

 

VIII. Acting as Neutral

 

IX. Ethical Issues.

 

A. Conflicts of Interest

B. Tainting of Bidders; Prior Relationship

C. A/E of Record

D. Selection Committee III. Risk Assessment and Contractual Solutions From the Perspective of the Design Consultant for a Construction Project Using Bridging-Design-Build Procurement

 

A. Introduction and Background – Setting the Stage

 

The managing principal of one of your design professional clients just called to engage you to assist it in the negotiation and drafting of its contract for a new project. You have represented the client for many years, but you have no prior knowledge about this particular project. The client is excited because it was chosen to provide the design for this unique, world-class project.

The client informs you that it is a large “bridging-design-build project”. The Client has been selected as the prime design professional for the Owner and will be called the “Bridging-Design ConsultantBridging Design Criteria Consultant”. The owner is a governmental entity and will use some form of bonds or certificates of participation to finance the Project.

She tells you that the firm’s scope of work for the Project is subject to clarification during the contract negotiation process but generally will consist of and include: