American Bar Association
Forum on the Construction Industry
PLENARY 8:
SHIPWRECKED:
Dealing With
Construction Contract Defaults in the Real World
(“The Surety Performance Bond
Lifeboat:
Bailing Out and/or Salvaging
Someone Else’s Wreck”)
George J. Bachrach
Whiteford, Taylor & Preston, LLP
October 25 & 26, 2007
Hyatt Regency Newport Hotel & Spa
©2007 American Bar Association
THE SURETY PERFORMANCE BOND LIFEBOAT:
BAILING OUT AND/OR SALVAGING SOMEONE ELSE’S WRECK
|
I. INTRODUCTION - SOME BACKGROUND ON SURETY BONDS…………….. |
2 |
|
|
|
|
II. THE SURETY’S DUTY TO INVESTIGATE |
|
|
A. Why the Surety has a Duty to Investigate…………………………………… |
4 |
|
B. When Does the Surety Investigate…………………………………………... |
5 |
|
C. The Who, What and How of the Surety’s Investigation…………………….. |
7 |
|
D. The Surety’s Analysis of its Investigation…………………………………... |
9 |
|
|
|
|
III. THE SURETY’S RIGHTS AND DEFENSES |
|
|
A. The Surety’s Assertion of the Principal’s Defenses…………………………. |
10 |
|
B. The Surety’s Assertion of its Own Defenses………………………………... |
13 |
|
|
|
|
IV. THE SURETY’S OBLIGATIONS AND OPTIONS |
|
|
A. Generally - The Surety’s Performance Bond Options………………………. |
19 |
|
B. The Takeover and Completion Option………………………………………. |
24 |
|
C. The Tender Option…………………………………………………………... |
29 |
|
D. The Financing the Principal Option…………………………………………. |
31 |
|
E. The Completion by the Obligee Option……………………………………... |
34 |
|
F. The Surety’s Denial of Liability Under the Performance Bond…………….. |
36 |
|
G. The Surety’s Failure to Perform Under the Performance Bond…………….. |
37 |
|
|
|
|
V. THE SURETY’S LIABILITIES UNDER THE PERFORMANCE BOND |
|
|
A. The Performance Bond Forms………………………………………………. |
40 |
|
B. The Obligee’s Claims for Damages…………………………………………. |
41 |
|
C. Extra-Contractual Damages…………………………………………………. |
43 |
|
|
|
|
VI. OTHER SURETY ISSUES ARISING FROM A PERFORMANCE |
|
|
BOND CLAIM |
|
|
A. The Surety’s Rights to the Contract Funds………………………………….. |
44 |
|
B. The Surety’s Rights Against the Principal and Indemnitors |
|
|
Under the Indemnity Agreement…………………………………………….. |
45 |
|
C. The Surety’s Rights Against Third Parties………………………………….. |
46 |
|
D. Alternative Dispute Resolution and Performance Bond Claims…………….. |
46 |
|
E. The Principal’s Bankruptcy and its Effects on an Obligee’s |
|
|
Performance Bond Claim……………………………………………………. |
47 |
|
|
|
|
VIII. SUMMARY AND CONCLUSION………………………………………………… |
47 |
|
|
|
|
APPENDIX - BIBLIOGRAPHY OF FREQUENTLY CITED SECONDARY |
|
|
MATERIALS………………………………………………………………... |
49 |
THE SURETY PERFORMANCE BOND
LIFEBOAT:
BAILING OUT AND/OR SALVAGING SOMEONE
ELSE’S WRECK
In
her companion paper to this paper entitled “Cross the Sea: Navigating the
Distressed Construction Project,” Deborah Butera discusses the issues of
default and termination of the construction contract, including the default
events and material breaches that may justify the termination of the
construction contract, the non-breaching party’s alternatives and options short
of a termination for default, and what occurs when there is a termination for
default (remedies and damages). These
issues, and many more, affect the surety that executes a performance bond and a
payment bond for its defaulted principal on a particular construction project.[1]
After
a brief discussion concerning the background of surety bonds, this paper will
be divided into three major sections concerning the surety’s immediate role
when there is an alleged and/or actual default and/or termination of the
principal’s construction contract. Those
sections include the following:
1. The surety’s duty to investigate
the obligee’s claim that the principal is in default under the construction
contract such that the obligee has the right to terminate the principal’s
construction contract;
2. The surety’s right to determine
if there are any defenses to the obligee’s claim against the surety’s
performance bond; and
3. The surety’s obligation, whether
or not there are any defenses to the obligee’s claim, to determine the surety’s
options under the performance bond and how best to exercise those options.
There
are other less immediate but still very important issues for the surety,
including the surety’s ultimate liability under the performance bond, the
surety’s rights to the contract funds from the defaulted construction contract,
the surety’s indemnity rights against and reimbursement rights from its
principal and indemnitors under the indemnity agreement, the surety’s rights
against third parties, and others, which will be discussed more generally and
briefly at the end of this paper.
The
goal of this paper is to provide a practical research tool and resource for
owners, architects, engineers, general contractors, subcontractors, and others
involved in the construction process and industry, and their counsel, by
accumulating in one place a summary and description of the surety’s duties,
rights and obligations when an obligee makes a claim against a surety’s
performance bond as a result of the obligee’s default and/or termination of the
principal’s construction contract.
I. INTRODUCTION -- SOME BACKGROUND ON SURETY BONDS[2]
Performance
and payment bonds are not insurance.
Rather, suretyship is a credit transaction.[3] In underwriting bonds for its principal, the
surety does not look at an actuarial analysis for assessing its risk of loss as
an insurer would do. Rather, the surety
looks at other factors, including the three “C’s” of contract surety
underwriting -- the principal’s cash, capacity and character. The three “C’s” evolve into three
questions. Does the principal have the
financial wherewithal, or cash, to continue the performance of the work
and the payment of the bills of the laborers, subcontractors and suppliers on
the construction project? Does the
principal have the capacity to perform the work (the necessary manpower,
both in quality and quantity; the technical ability and construction expertise
to timely and correctly perform and complete the work; and the home office
expertise, including accounting expertise, record keeping and other backup services,
to ensure that the principal’s progress in performing the work can be
accurately measured and computed)? Does
the principal have the character (the honesty, integrity,
trustworthiness and commitment to complete the work on the construction
contract) that is critical to the success of both the construction project and
the principal and surety relationship?
The
surety also makes other judgments in determining whether to write bonds for the
principal. The principal’s expertise in
the kind or type of work to be performed; the location of the construction
project; the total amount of the principal’s work program that is outstanding;
the scope of work, contract price and time of completion (duration) of the
particular construction contract, especially in light of the prior construction
contracts the surety has bonded for the principal; the added complexity that
various contract and performance bond terms and requirements may add to the
scope and performance of the work (including design-build, performance-based
specifications, “onerous” bond provisions and others); and other factors weigh
heavily on the surety’s decision to write the performance and payment bonds for
a particular construction project.
Practically
every performance bond is different from every other performance bond.[4] Both the principal and the surety execute the
performance bond in favor of the obligee.[5] Normally, the principal and the surety are
jointly liable under the performance bond so long as any applicable conditions
precedent are met.
In
summary, the universe of obligees requests bonds from the principal and the
surety in order to assure themselves that the construction contract will be
performed and completed for the agreed upon consideration. In the vast majority of cases, the obligee
procures the bonds from the principal and the surety, sticks them in the file,
and never looks at them again. However,
when the obligee alleges that the principal is in default and advances toward a
termination of the principal’s construction contract, the bonds may become the
performance life boat for the obligee that wants the surety to bail out and/or
salvage what the obligee considers to be the principal’s wreck of the
construction project.
II. THE SURETY’S DUTY TO INVESTIGATE
A. Why
the Surety has a Duty to Investigate[6]
In any construction project, the principal
and the surety have a whole set of legal, contractual, equitable and statutory
obligations to many parties that are not shared by the obligee. The obligee looks to the obligations of the
principal to complete the performance of the work under the construction
contract and to the obligations of the surety to guarantee that
performance. However, the principal and
the surety may have obligations to the principal’s laborers, subcontractors and
suppliers on the construction project and the lower-tier entities that have
contractual relationships with those subcontractors and suppliers. Furthermore, the principal, third-party
individual and corporate indemnitors, and the surety may have a contractual
relationship in the form of an indemnity agreement to support the surety’s
execution of the bonds. Finally, there
are other relevant third parties, such as banks, taxing authorities, judgment
creditors and other entities that may have an interest in the principal’s
performance of the work (and collection of the contract funds).[7] Regardless of the outstanding disputes, the
surety must investigate the facts before it may arrive at any conclusions and
decisions.
When a default and/or termination either is
imminent or has occurred, the surety has to determine whether there are any
defenses to the obligee’s claim and the various facts necessary in order for
the surety to determine its options.
There may be conflicts in the various obligations of the principal and
the surety to the obligee and others.
Those conflicts may escalate when the obligee and the principal are in
dispute about whether there is, in fact, a default, and who is in default,
thereby placing the surety in the “classic dilemma.”[8] Why does a surety have a duty to
investigate? It is because the surety
has many parties that it has to answer to as it attempts to learn the facts
about the situation and make its decisions.
B. When Does the Surety Investigate
Many performance bond forms set conditions
precedent for when a surety must perform its obligations under the performance
bond. As will be seen later in this
paper, the obligee’s failure to meet those conditions precedent may result in a
surety being released and discharged from its obligations under the performance
bond. However, there are few, if any,
performance bonds that describe when a surety must begin its investigation[9]
into an impending obligee default and/or termination of the principal.[10]
For
example, the AIA Document A311 Performance Bond (1970) provides that:
Whenever Contractor shall be, and declared
by Owner to be in default under the Contract, the Owner having performed
Owner’s obligations thereunder, the Surety may . . .
take certain actions,
and the performance bond then outlines various options for the surety. This language sets three conditions precedent
before the obligee has rights against the surety under the performance bond --
the principal is in default, the principal is declared by the obligee to be in
default, and the obligee has performed its obligations under the contract.[11] One unanswered question is when the surety’s
duty to investigate arises under this performance bond.
For
another example, the AIA Document A312 Performance Bond (1984), paragraph 3,
provides that, if there is no Owner Default,[12]
the surety’s obligation arises after the obligee complies with the performance
bond’s conditions precedent:[13]
3.1 The
Owner has notified the Contractor and the Surety at its address described in
Paragraph 10 below that the Owner is considering declaring a Contractor Default[14]
and has requested and attempted to arrange a conference with the Contractor and
the Surety to be held not later than fifteen days after receipt of such notice
to discuss methods of performing the Construction Contract. If the Owner, the Contractor and the Surety
agree, the Contractor shall be allowed a reasonable time to perform the
Construction Contract,[15]
but such an agreement shall not waive the Owner’s right, if any, subsequently
to declare a Contractor Default; and
3.2 The
Owner has declared a Contractor Default and formally terminated the
Contractor’s right to complete the contract.
Such Contractor Default shall not be declared earlier than twenty days after
the Contractor and the Surety has received notice as provided in Subparagraph
3.1; and
3.3 The
Owner has agreed to pay the Balance of the Contract Price[16]
to the Surety in accordance with the terms of
the Construction Contract or to a contractor
selected to perform the Construction Contract in accordance with the terms of
the contract with the Owner.
Arguably,
the surety may begin its investigation prior to the date set for the conference
required under paragraph 3.1 of this performance bond. However, there is a large difference between
a surety’s investigation of whether, as the obligee alleges, the principal is
in default under the construction contract, especially when the principal
disputes that it is in default, and a surety’s investigation after the
obligee’s termination of the principal’s construction contract in order to
determine and/or exercise the surety’s options under the performance bond.
Neither
the AIA Document A311 Performance Bond nor the AIA Document A312 Performance
Bond provides some defined time when the surety has a duty to investigate. Some obligees routinely and regularly claim
that the principal is in default during the course of construction for minor,
not so minor and/or more material breaches of the construction contract, and
send notices to the surety of these alleged breaches and defaults on a frequent
basis, usually as a copy of a letter directed to the principal. Do such notices trigger the surety’s duty to
investigate? Different sureties take
different positions on whether the surety has a duty to investigate prior to
the obligee’s complying with the performance bond’s conditions precedent,
thereby triggering the surety’s performance obligations under the performance
bond. It is beyond the scope of this
paper to delve deeply into when the surety must commence its duty to
investigate. Other commentators have
written extensively on the surety’s duty to investigate and when that occurs in
conjunction with the acts and events triggering the surety’s performance
obligations under the performance bond.[17]
C. The Who, What and How of the Surety’s
Investigation
There
is a difference in the who, what and how of a surety’s investigation when the
situation is whether the principal is in default under the construction contract
(and whether the surety may have the obligation to perform under its
performance bond) as compared with the situation when the principal is actually
in default and the obligee has terminated the principal’s construction
contract, with the surety investigating its performance obligations and options
under the performance bond. However, for
this paper, I will treat the who, what and how of the surety’s investigation in
one place.
When
the surety investigates a performance bond claim, the commentators have
described a number of sources for the facts, information and documents that a
surety may require.[18] The sources and kinds of information that the
surety may seek during its investigation generally include the following:
1. A review of the surety’s underwriting
files and documents to support the bonds themselves, including a thorough
review of the actual performance and payment bonds, the construction contract,
the bidders on the project and the bid spreads, any job status inquiries, and
all other documents.
2. A review of the principal’s books and
records for the construction contract, including a complete set of the contract
documents, change orders, pending change orders, general and special
conditions, specifications and drawings; copies of all progress estimates
and/or payment applications; lists of all subcontracts and purchase orders,
and, if appropriate, copies of those documents; all accounts payable and
accounts receivable; the bid estimate file; and job correspondence.
3. A review of the obligee’s books and
records for all of the construction contract documents, including the plans and
specifications, all change orders (approved, pending and denied) and
backcharges, job minutes, progress reports and punchlists; copies of all
progress estimates and/or payment applications; job schedules; any lists of
notices from the principal, subcontractors and suppliers of nonpayment; and all
job correspondence between the obligee and the principal. Very importantly, the obligee must provide
the surety with fully executed copies of the performance and payment bond.[19]
4. The surety may comply with and want to
visit the bonded project site(s) to determine the state of the completion of
the performance of the work and inventory any materials stored on the premises
for use in the performance of the work.
The surety may also want to review the project schedule(s) that may be
located at the project site(s).
5. Assuming that the surety has received
payment bond claims from the principal’s subcontractors and suppliers on the
bonded contract(s), the surety will investigate the factual basis for and
resolve those claims in compliance with the terms of the relevant payment
bond(s).
D. The Surety’s Analysis of its
Investigation
There
is never enough time for a surety to complete a full investigation before it
may be required to make a decision on whether and/or how to perform under the
surety’s performance bond. A surety’s
investigation reviews many issues, including the following:
1. Why the performance bond claim arose.
2.
Whether the obligee’s termination
of the principal for default is proper and justified under the construction
contract[20]
and whether the obligee has complied with any conditions precedent under the
performance bond such that the surety is obligated to perform under the
performance bond.[21]
3. Whether the surety may assert any of
the principal’s defenses (see Section
III. A. below) or assert its own surety defenses (see Section III. B. below) to the obligee’s performance bond claim.
4. How the surety may comply with and
fulfill its performance bond obligations and its options under the performance
bond while controlling and/or mitigating its loss exposure (see Section IV. below).
5. How the surety may recover its losses
through indemnity, salvage, subrogation or other means (see Section VI. A., B. and C. below).
At
some point, promptly after its analysis of its investigation, a surety will
make a decision. The basis for the
surety’s decision and the consequences of that decision are the subject of
Sections III. and IV. below.
III. THE SURETY’S RIGHTS AND DEFENSES
In
a default and/or termination scenario, it is rare that a surety may fully
perform the definitive detailed investigation that it would like before it must
determine what steps to take. The
critical documents to review are the performance bond and the construction
contract as they set out the rights and obligations of the three parties -- the
obligee, the principal and the surety.
Once the investigation is as complete as possible under the various time
constraints, the surety must analyze its rights, which include possible
defenses to the obligee’s claims against the performance bond, and its options
going forward, whether they are spelled out specifically within the performance
bond or not.
A. The Surety’s Assertion of the Principal’s Defenses
Many
performance bonds require not only that the principal be in default and/or
declared by the obligee to be in default under the construction contract, but
also that the obligee must have performed the obligee’s obligations under the
construction contract. That is true
under both the AIA Document A311 Performance Bond (“the Owner having performed
Owner’s obligations” under the construction contract) and the AIA Document A312
Performance Bond (“[i]f there is no Owner Default,” which is defined in
paragraph 12.4 of the AIA Document A312 Performance Bond as the “[f]ailure of
the Owner, which has neither been remedied nor waived, to pay the Contractor as
required by the Construction Contract or to perform and complete or comply with
the other terms thereof”). If the
obligee is in default under the construction contract, the principal may have a
defense to the obligee’s termination of the principal’s construction contract,
and the surety may assert the principal’s defenses when the obligee makes a
claim against the performance bond.[22]
Listed
below are a number of the principal’s defenses that the surety may assert. During the surety’s investigation and
analysis, there may be other defenses that the principal may assert that the
surety may discover. There are a number
of books, articles and papers that discuss the surety’s assertion of the
principal’s defenses against an obligee’s performance bond claim, and some of
the most relevant and helpful are listed in the footnote below.[23]
1. The obligee’s wrongful termination of
the principal’s construction contract.[24]
2. The obligee’s failure to pay the
contract funds.[25]
Obviously,
if the obligee wrongfully fails to pay the principal the contract funds, the
principal may have a defense as a result of the obligee’s material breach of
the construction contract.
3. The obligee’s duties incident to the
project’s design.
If
the obligee fails to fulfill its duties incident to the design of the project,
including but not limited to the obligee’s failure to provide plans and
specifications that are free from defects, the principal may be discharged from
its performance under the construction contract. The obligee’s duties include the following: [26]
a. The obligee’s implied warranty of
design adequacy (including the “government contractor” defense[27]).
b. The obligee’s implied warranty of
commercial availability of specified construction materials.
c. The obligee’s implied duty of
disclosure.
d. The blending of design and performance
specifications.
e. The obligee’s approval of the
principal’s work plan.
f. The obligee’s implied warranty of
design versus the principal’s warranty of materials.
g. The obligee’s responsibility for latent
ambiguities in its design.
4. The obligee’s implied duty of
cooperation.[28]
5. The impossibility or impracticality of
the performance of the work.[29]
6. The obligee’s failure to properly
administer the construction contract (including the obligee’s lack of response
to requests for information and proposed change orders and other failures to
act timely).[30]
7. The obligee’s failure to provide the
principal with an opportunity to cure the default.[31]
8. The obligee’s implied waiver of
contract requirements.[32]
9. The obligee’s insistence upon strict
compliance in the face of economic waste, and hypertechnical inspection.[33]
10. The obligee’s release and settlement of
claims against the principal.[34]
11. The principal’s setoffs and/or
counterclaims.[35]
B. The Surety’s Assertion of its Own Defenses
Along
with the defenses of its principal, the surety may assert its own defenses to
an obligee’s performance bond claim.
Listed below are a number of the surety’s defenses to an obligee’s
performance bond claim after the default and termination of the principal on
the construction contract, with citations to the books, articles and papers
that discuss the surety’s defenses against an obligee’s performance bond claim.
1. The release and/or discharge of the
surety’s principal (including but not limited to the obligee’s wrongful
termination of the principal’s construction contract).[36]
2. The obligee’s failure to provide notice
to the surety and/or to comply with the performance bond’s conditions precedent
requiring the surety to perform (including the obligee’s failure to allow the
surety to have the opportunity to exercise and/or perform its options under the
performance bond).
During
the surety’s investigation and analysis, the surety attempts to determine from the
facts gathered and its legal review what constitutes a principal’s alleged
construction contract default so that an obligee may require the surety to
perform its obligations under the performance bond.[37] In making its analysis, the surety will
review the distinction between a breach of contract and a default,[38]
what is a material breach of contract,[39]
whether the construction contract provisions defining a “default” or an “event
of default” are the exclusive grounds for determining the principal’s default,
or whether there are other grounds,[40]
and the obligee’s potential waiver of the principal’s default.[41]
In
addition, many courts have found that the surety may be entitled to a notice[42]
from the obligee of the obligee’s declaration of the principal’s default.[43] Some courts have found differently and
concluded that such an obligee notice to the surety is unnecessary.[44] There may be consequences to the obligee if
the required notice of its declaration of a principal’s default is not provided
to the surety. If the notice to the
surety is a condition precedent for the surety to perform its obligations under
the performance bond, the surety may be released from all of its liability to
the obligee under the performance bond because of the obligee’s failure to provide
the surety with such notice.[45] In other cases, however, the obligee’s
failure to provide such notice to the surety may only reduce the surety’s
liability under the performance bond to the extent that the surety has been
prejudiced or harmed as a result of not receiving the obligee’s notice of the
declaration of the principal’s default.[46]
Finally,
whether or not the obligee has provided the surety with notice of the obligee’s
declaration of the principal’s default under the construction contract, if the
obligee takes actions that deny the surety the ability to exercise its rights
to perform under the performance bond, the surety may be released and
discharged from any liability to the obligee under the performance bond.[47]
3. The principal’s substantial performance
of the construction contract.[48]
4. The obligee’s actions that are
prejudicial to the surety.
a. Material alterations to the
construction contract (cardinal changes).[49]
b. Overpayments or improper payments -
impairment or release of collateral (the bonded contract funds).[50]
c. Extensions
of time.[51]
d. The failure to give timely notice[52]
and/or to timely default and terminate the principal.[53]
e. The
obligee’s failure to mitigate its damages.[54]
f. Other
obligee actions, including changes in the obligee or the principal.[55]
5. Contractual and statutory limitations.[56]
6. The obligee’s lack of good faith
(concealment, non-disclosure and/or misrepresentation of facts).[57]
IV. THE SURETY’S OBLIGATIONS AND OPTIONS
In
order to adequately discuss the surety’s obligations and its options in a
performance bond situation, we have to assume that there is a valid obligee
default and/or termination of the principal’s construction contract such that
the surety has no defenses to the performance bond claim and is obligated to
perform under the terms of the performance bond. The one caveat to this assumption is that the
surety may elect to perform under the performance bond despite the principal’s
and/or the surety’s disputes with the obligee for a myriad of reasons, while
reserving all of its and their rights and defenses, including the principal’s
defenses and the surety’s defenses mentioned above.
A. Generally - The Surety’s Performance Bond Options
A
frequent reaction of a surety lawyer or in-house surety claims representative
when the obligee terminates the principal’s construction contract and makes a
claim against the surety’s performance bond is that the surety has a number of
options. The most common surety
performance bond options are discussed in this Section IV. of the paper. However, it is important for the surety to
complete its investigation of its performance bond obligations and determine
its best options. In order to do so, the
surety may take the following actions.
1. Read the performance bond.
It
is critical for the surety to review the executed performance bond for the
construction contract. Both the AIA
Document A311 Performance Bond[58]
and the AIA Document A312 Performance Bond[59]
provide that the surety may exercise certain performance options. While the obligee and the surety may later
negotiate any changes they want to make concerning their respective rights and
obligations, if no other agreement can be reached, then the terms of the
performance bond will dictate what happens next. There are many types of performance bond
forms,[60]
and the acronym “RTFB” could not be more accurate when the obligee makes a
claim against the surety’s performance bond.
2. Read the construction contract.
The
construction contract is referred to and may be incorporated by reference into
the surety’s performance bond.
Therefore, the provisions of the construction contract may inevitably be
read into the performance bond at least to the extent of the major terms
concerning the scope of the principal’s work, the contract price and the terms
of payment. The time of completion,
however, may not be binding upon the surety depending upon the circumstances
and timing of the obligee’s default and termination of the principal.[61] Furthermore, certain provisions, such as an
arbitration provision in a construction contract that has been incorporated by
reference into the surety’s performance bond, may or may not compel the surety
to participate in any arbitration between the obligee and the principal.[62]
3. Read any applicable statutes,
regulations and/or federal/state law.
Many
performance bonds are regulated by statute (either the Federal Miller Act or
the various State Little Miller Acts).
Numerous cases discuss a surety’s liabilities under its statutory
performance bond and read the provisions of the statute into the performance
bond in order to extend the surety’s obligations to those required by statute.[63] Some states, and certainly the federal
government, [64]
have regulations that are applicable to an obligee’s termination of the
principal’s construction contract and the surety’s options under the
performance bond. Finally, there are
federal and state cases that discuss the particular jurisdiction’s applicable
law for performance bonds.[65]
4. Affirm and protect the penal sum of the
performance bond.
Regardless
of the terms of the performance bond, the construction contract and the
applicable statute and regulations, in exercising any performance bond option,
the surety must affirm and protect the penal sum of the performance bond. In choosing its option, the surety must be
aware of the risks in each option that it may explore and determine in each
situation if any one or more of the options may expose the surety to liability
in an amount in excess of the penal sum of the performance bond. In any such factual situation, the surety may
well have to discard one or more of its performance bond options when such a
risk exists.[66]
5. Understand the three critical
performance issues.
Every
termination for default that results in the surety’s performance under the
performance bond has its own set of critical issues. What may be an important issue on one project
may not be on another project, and vise versa.
However, the issues discussed below are the three critical issues that
the surety and the obligee (and/or any prospective completion contractor, if
applicable) try to resolve up front (with the exception of when a surety denies
liability to an obligee under the performance bond) in any situation when the
surety performs under its performance bond.
a. The scope of the remaining work.
The
original construction contract normally contains a relatively detailed
description of the principal’s scope of the work to be performed. Whether the principal is a general contractor
on the project (and the scope of the work is building the building or
constructing the roadway) or the principal is a subcontractor to the general
contractor on the project (putting in the electrical work or plumbing work in
the building or striping the roadway), the work to be performed under the
construction contract by the surety under its performance bond should be
ascertainable. When the obligee
terminates the principal for default, the remaining scope of work may become an
issue. During construction, the scope of
the principal’s work may change due to various change orders and other
factors. With the exception of the
surety’s correction of any defective work that the principal may have
performed, there may be an issue of whether the obligee expects the surety to
perform work in addition to and outside the scope of the principal’s original
construction contract, all at the surety’s cost and expense. The surety, during its investigation of its
performance bond options, will attempt to determine the scope of the remaining
work to be performed in order to adequately define that remaining scope of work
required by its performance bond obligations.
b. The balance of the contract price and
payment to the surety.
Similarly,
the balance of the contract price, or the amount of the remaining contract
funds, is clearly an issue that must be resolved between the obligee and the
surety in order for the surety to determine its ultimate loss. Both the AIA Document A311 Performance Bond
and the AIA Document A312 Performance Bond provide that the “balance of the
contract price” will be available to the surety that performs under the
performance bond. The penal sum of the
performance bond is in an amount equal to the original construction contract
price, and the surety expects that the remaining contract funds will be used to
complete the performance of the project and reduce the surety’s loss. To the extent that the performance of the
work costs the surety monies in excess of the remaining balance of the contract
price, the surety will fund the excess costs with the expectation that the
excess costs will define its ultimate liability under the performance bond.
c. The time of completion.
In
most situations when the obligee has terminated the principal for default, the
time of completion of the original construction contract has either passed or
is rapidly approaching. Depending upon
the facts and the performance bond option that the surety may exercise, the
time of completion issue between the obligee and the surety may become a large
dispute. Conceivably, by its failure to
terminate the principal for default until the time of completion is close to
the end with a lot of work to be performed, the obligee may have waived its
right to obtain timely performance of the construction contract.[67] Furthermore, there may be disputes between
the obligee and the principal concerning the party or parties who have caused
the delays in the time of completion, with the principal contending that it is
entitled to additional time for the performance of the construction contract
and additional payments for its damages due to the delays caused by others. Finally, depending upon the performance bond
option the surety exercises, the surety may be entitled to a reasonable amount
of time (and, possibly, a time extension) to perform the work under a takeover
agreement or other surety performance bond option.[68]
6. Summary of the surety’s performance
bond options.
Generally,
the surety may have a number of performance bond options when the obligee
terminates the principal’s construction contract, including the options to take
over and complete, tender, finance the principal, work with the obligee to
complete (and/or “buy back” the performance bond) and/or deny liability under
the performance bond.[69] Each of these separate options will be
discussed more fully below.[70]
B. The Takeover and Completion Option
Upon
the principal’s termination for default, the surety may take over the
performance of the work and complete the performance of the work using the
services of a completion contractor.
Frequently, the surety enters into a separate takeover agreement with
the obligee that specifies, among other things, the amount of the balance of
the contract price, the scope of the work required to complete the performance
of the work under the construction contract, and the time of completion. The takeover agreement (and normally the
performance bond, too) requires the obligee to dedicate the balance of the
contract price to the completion of the construction contract, with the surety
agreeing to pay the excess costs of completion up to the penal sum of the
performance bond. The surety will then
enter into a separate contract with a completion contractor to actually perform
the work.
1. Prior articles.
There
are a number of books, articles and papers that discuss the surety’s takeover
and completion option, and some of the most relevant and helpful are listed in
the footnote below.[71]
2. The provisions of the performance bond.
a. Pursuant to the AIA Document A311
Performance Bond, the surety may “[c]omplete the Contract in accordance with
its terms and conditions.” Allowing the
surety to complete the construction contract in accordance with its terms and
conditions essentially authorizes the surety’s option to take over and complete
the performance of the work. The surety
expects to be paid the balance of the contract price, with the surety paying
any excess costs of completion.
b. Pursuant to the AIA Document A312
Performance Bond, the surety may:
4.2 Undertake
to perform and complete the Construction Contract itself, through its agents or
through independent contractors . . . .
Paragraph 4.2
recognizes the surety’s option to take over and complete the construction
contract through the surety’s “agents” or through “independent contracts.”[72]
3. The documents.
a. The Takeover Agreement between the obligee
and the surety.[73]
In
order for the surety to takeover and complete the performance of the work under
the principal’s construction contract, the surety and the obligee may enter
into a Takeover Agreement to define their respective rights, duties and
obligations. The three major issues that
must be dealt with in a Takeover Agreement are the scope of the remaining work
to be performed by the surety through its completion contractor, the remaining
balance of the contract price and payment (the amount of the original contract
price between the obligee and the principal, plus or minus any approved
additive or deductive change orders, and minus any payments properly made by
the obligee to the principal, all subject to a reservation of rights by the
surety to verify the accuracy of the remaining contract funds) and the time of
completion.[74] Normally, the original construction contract
between the obligee and the principal is incorporated by reference into the
Takeover Agreement. In the event that
the principal disputes the obligee’s termination for default, the Takeover
Agreement may have a reservation of rights section to preserve the ability of
the principal and/or the surety to contest the obligee’s termination of the
principal for default and obtain damages for that wrongful termination.
b. The Completion Contract between the
surety and the completion contractor.[75]
Because
the surety itself will not be performing the work for the obligee under the
Takeover Agreement, the surety will “subcontract” that work to a completion
contractor. The Completion Contract
deals with many of the same issues as the Takeover Agreement, including a
definition of the completion contractor’s scope of the work, the contract price
that the surety will pay the completion contractor to perform the work, and the
time for the completion contractor’s performance of the work. The Completion Contract is like many other
construction contracts with respect to its terms and conditions.
4. The critical issues.
In
addition to the issues of the scope of work, the balance of the contract price
and payment, and the time of completion, the surety in the Takeover Agreement
with the obligee and in the Completion Contract with the completion contractor
may deal with other critical issues.
With
respect to the Takeover Agreement between the obligee and the surety, the
Takeover Agreement may address such issues as the procedures for the discovery
and correction of any defective work performed by or the performance of any
warranty work required of the terminated principal; the surety’s representative
on the construction project, including his or her scope of responsibility and
extent of authority; the surety’s reservation of any rights or claims; the
location of any stored materials and the transfer of title to the surety;
insurance issues (both prior to the termination and ongoing during the takeover
and completion) and others.[76]
The
preservation of the penal sum of the performance bond (and the companion
payment bond) is the surety’s issue, not the obligee’s issue. In determining its performance bond options,
the surety will zealously guard against making payments that exceed the penal
sum of the performance bond. Furthermore,
in most Takeover Agreements, the surety requires the obligee to acknowledge
that the surety’s liability for the excess cost of completion of the
performance of the work under the performance bond is limited to the penal sum
of the performance bond (with a similar provision concerning the payment bond).[77]
With
respect to the Completion Contract between the surety and the completion
contractor, in addition to having the completion contractor be bound to the
same scope of work, time of performance, and price (including the surety’s
payment of the completion contractor’s excess costs to complete the performance
of the work over and above the “balance of the contract price” owed by the
obligee to the surety) and payment obligations as the surety is bound to the
obligee under the Takeover Agreement, the surety will want the completion
contractor’s insurance to serve as the surety’s insurance for the obligee as
well as for the surety under the Completion Contract. Other issues include the requirement of
performance and payment bonds from the completion contract to the surety; the resolution
of any contract claims, including the prosecution and payment of any
pass-through claims to the obligee; the completion contractor’s performance of
the work to correct any alleged latent defective work performed by the
principal and to perform any warranty work required by the scope of work under
the construction contract, as well as the surety’s payment to the completion
contractor, if any, for that work; how any disputes between the surety and the
completion contractor are resolved, whether or not they involve the obligee;
and others.[78]
5. The
surety’s takeover under the terms of the performance bond.
At
times, an obligee will refuse to enter into a Takeover Agreement with the
surety, taking the position that it already has a contract with the surety
called a “performance bond” and that it does not need an additional document to
have the surety perform under that performance bond. If the terms of the relevant performance bond
essentially require the surety to complete the performance of the work in
accordance with the terms of the construction contract, the surety may be
required to undertake that completion effort as long as it has no other
defenses to the obligee’s claim against the performance bond. The surety will then contract with a completion
contractor to perform the work and will operate under the performance bond and
the original construction contract.
Sureties
generally prefer to enter into a written Takeover Agreement with the obligee in
order to resolve a number of issues (including but not limited to the manner
and method of payment, the surety’s rights to the contract funds, the
resolution of change orders, the correction of the principal’s defective work
and others) up front that will make the ongoing working relationship between
the surety and the obligee easier as the work proceeds. For example, the terminology in the
performance bond and the construction contract may become confusing when the principal
(the former contractor) is replaced by the surety using the services of its
completion contractor.
Notwithstanding
the obligee’s refusal to execute a Takeover Agreement, the surety needs
something in writing that confirms that the surety is taking over the
construction contract pursuant to the performance bond. Whether this is a contract modification
signed by the obligee (at least to substitute the surety as the “contractor”
under the construction contract, and any other such “clarifications”) or a
detailed letter from the surety to the obligee setting forth the surety’s
understandings of the takeover arrangement and reserving the surety’s rights,
such writings at least provide the surety with some confirmation of the
obligee’s demand and the resulting basis for the surety’s actions.
C. The Tender Option
A
tender agreement is similar to a takeover agreement, except that the
contracting parties are ultimately the obligee and the completion contractor
with the support of the surety.
Typically, a three-way agreement is reached under which the obligee
agrees to allow the completion contractor to complete the performance of the
work that was originally required by the terminated principal directly for the
obligee for a set contract price. To the
extent that the new contract price between the obligee and the completion
contractor exceeds the balance of the contract price under the original
construction contract between the obligee and the terminated principal, the
surety agrees to pay the excess costs of completion to the obligee for its eventual
distribution to the completion contractor, either in a lump sum or as the work
is performed and completed. The surety
should then be released from its performance bond obligations upon payment of
the excess costs of completion to the obligee.
1. Prior articles.
There
are a number of books, articles and papers that discuss the surety’s tender
option, and the most relevant and helpful is listed in the footnote below.[79]
2. The provisions of the performance bond.
a. Pursuant to the AIA Document A311
Performance Bond, the surety may:
2)
Obtain a bid or bids for
completing the Contract in accordance with its terms and conditions, and upon
determination by Surety of the lowest responsible bidder, or, if the Owner
elects, upon determination by the Owner and the Surety jointly of the lowest
responsible bidder, arrange for a contract between such bidder and Owner, and
make available as Work progresses (even though there should be a default or a
succession of defaults under the contract or contracts of completion arranged
under this paragraph) sufficient funds to pay the cost of completion less the
balance of the contract price; but not exceeding, including other costs and
damages for which the Surety may be liable hereunder, the amount set forth in
the first paragraph hereof. The term
“balance of the contract price,” as used in this paragraph, shall mean the
total amount payable by Owner to Contractor under the Contract and any
amendments thereto, less the amount properly paid by Owner to Contractor.
This provision
provides the surety with a tender option.
b. Pursuant to the AIA Document A312
Performance Bond, the surety may:
4.3 Obtain
bids or negotiated proposals from qualified contractors acceptable to the Owner
for a contract for performance and completion of the Construction Contract,
arrange for a contract to be prepared for execution by the Owner and the
contractor selected with the Owner’s concurrence, to be secured with
performance and payment bonds executed by a qualified surety equivalent to the
bonds issued on the Construction Contract, and pay to the Owner the amount of
damages as described in Paragraph 6 in excess of the Balance of the Contract
Price incurred by the Owner resulting from the Contractor’s default;
This provision provides
the surety with a tender option.
3. The documents.
A
Tender Agreement[80]
may be a three-party agreement between the obligee, the surety and the
completion contractor (although there may be a separate Tender Agreement
between the obligee and the surety and a separate Completion Contract between
the obligee and the completion contractor, with both documents being executed
simultaneously). In a Tender Agreement
situation, the surety negotiates what is essentially a direct contract between
the obligee and the completion contractor that results in the completion of the
work to be performed under the default terminated construction contract. To the extent that the surety must fund the
excess costs of completion (over and above the “balance of the contract
price”), it may do so on a periodic basis or on a lump-sum basis or other
basis, depending upon the negotiations.
The surety will also want a release from its performance bond obligation
once it has “performed” by tendering a completion contractor to the obligee and
paying the excess costs of completion, if any.
4. The critical issues.
The
critical issues of the scope of work, the balance of the contract price and the
time of completion are always important in any performance bond claim and
resolution. However, a fourth issue that
is critical to the surety is the release of the surety from all or a portion of
its obligations under the performance bond.
Unlike the takeover and completion scenario, when the surety remains
involved in what is going on during the completion of the performance of the
work and, therefore, has some control over its ultimate risks, in the tender
option, the surety is relying on the obligee and the completion contractor to
complete the performance of the work without the surety’s involvement or
presence. The surety will seek a release
from any further liability under the
performance bond when it believes it has paid the obligee a sufficient premium in
price to cover whatever the obligee may owe and pay to the completion contractor,
including amounts for any unknown events that may occur. The obligee may or may not be willing to
provide the surety with such a release, which may go to the heart of the
surety’s decision on whether to tender a completion contractor to the obligee
or maintain control of its risk by taking over the construction project itself
and subcontracting directly with the completion contractor.
D. The Financing the Principal Option
There
is an option that a surety may exercise in order to “perform” under its
performance bond either prior to or after the obligee’s
actual default and/or termination of the principal under the construction
contract. In the event that a surety
learns that its principal is having financial difficulties and may face a default
termination situation, a surety may determine that it is in the best interests
of the principal, the obligee, the principal’s subcontractors and suppliers and
the surety for the surety to finance the principal’s completion of the
performance of the work required by the construction contract. Surety financing is a mechanism under which
the surety may remedy its principal’s potential or existing defaults and avoid
the obligee’s termination of the principal’s right to proceed to perform the
work under the construction contract.
The benefits of a surety financing its principal are that the work
continues to be performed on a timely basis because no default or termination
is necessary, and, therefore, no delays are caused by the obligee’s termination
of the principal. Early intervention by
a financing surety may preserve the surety’s options going forward and provide
the surety with better control of the outcome of any claims and potential
losses.
The
surety’s financing may take a number of forms, including direct surety advances
to its principal, the surety’s guaranty of a bank loan to its principal, “back
door financing” and other methods. However, it is clear that a surety financing
its principal’s completion of the performance of the work may constitute the
surety’s “performance” under the performance bond.[81]
1. Prior articles.
There
are a number of books, articles and papers that discuss the surety’s financing
of its principal option, and some of the most relevant and helpful are listed
in the footnote below.[82]
2. The provisions of the performance bond.
a. Pursuant to the AIA Document A311
Performance Bond:
. . .
the Surety may promptly remedy the default, or shall promptly
1) Complete
the Contract in accordance with its terms and conditions,
. . . .
When a surety is
authorized to “promptly remedy the default” and to “[c]omplete the Contract in
accordance with its terms and conditions,” the surety may accomplish both by
financing the principal.
b. Pursuant to the AIA Document A312
Performance Bond, the surety may:
4.1 Arrange
for the Contractor, with consent of the Owner, to perform and complete the
Construction Contract; . . . . [83]
This provision
authorizes the surety’s financing of its principal to perform and complete the
work required under the construction contract with the obligee’s consent.
3. The documents.
When
the surety makes a decision to finance its principal’s completion of the
performance of the work, the surety and the principal, and any third-party
indemnitors, may execute a Financing and Collateral Agreement or such other
agreement and related documents that defines the rights, duties, obligations,
mechanisms and procedures for the surety’s financing.[84]
4. The critical issues.
There
are many critical issues for the surety financing the principal’s completion of
the performance of the work, which is one very good reason why sureties are
disinclined to use the financing option.
While the principal may not have sufficient cash to complete the
performance of the work, the surety must be assured that the principal is
capable of performing the remaining work properly, and without defect, and on a
timely basis. Furthermore, the character
of the principal and the third-party indemnitors is especially important
because the surety is working with them on a daily, weekly and monthly basis to
mitigate its and their loss and damage.
E. The Completion by the Obligee Option
Under
certain circumstances, and if its actions do not violate the surety’s rights
under the performance bond and/or risk the release and discharge of the
surety’s performance bond, the obligee may determine that it will complete the
performance of the work of the terminated principal through its own completion
contractor, and use the balance of the contract price to fund the completion of
the work.[85] Subsequently, if the costs to complete the
performance of the work exceed the balance of the contract price, and if the
obligee has not waived or released its rights against the performance bond, the
obligee will make a claim against the surety under the performance bond for the
excess costs to complete the performance of the work and any other damages the
obligee claims. The surety may consent
to the obligee’s actions and agree to pay the excess costs of completion, either
in whole or in part, depending upon whether or not the surety contends that it
is not liable for certain of the alleged excess costs to complete the
performance of the work and some or all of the other damages the obligee
claims.
A
second variation in the obligee completion option is that the obligee and the
surety come to some agreement concerning the excess costs to complete the
performance of the work, and the surety pays that amount to the obligee in
return for a complete release and discharge of the performance bond. This variation is frequently referred to as
the “buy back” option and may be used whether or not the estimated excess cost
to complete the performance of the work is less than, equal to or greater than
the penal sum of the performance bond.
The “buy back” option may be attractive to both the obligee, who may
need a quick infusion of cash to complete the project, and the surety, because
it offers a quick resolution to the problem without exposing the surety to
liability in excess of the penal sum of the performance bond.
1. Prior articles.
There
are a number of books, articles and papers that discuss the completion by the
obligee option, and the most relevant and helpful is listed in the footnote
below.[86]
2. The provisions of the performance bond.
a. The provisions of the AIA Document A311
Performance Bond do not specifically state a completion by the obligee
option. However, there is nothing under
that performance bond that prohibits the obligee and the surety from agreeing
that the obligee may complete the performance of the work under the
construction contract and claim the excess costs of completion, if any, under
the performance bond.
b. Pursuant to the AIA Document A312
Performance Bond, the surety may:
4.4 Waive
its right to perform and complete, arrange for completion, or obtain a new
contractor and with reasonable promptness under the circumstances:
.1 After
investigation, determine the amount for which it may be liable to the Owner
and, as soon as practicable after the amount is determined, tender payment
therefor to the Owner;
This
provision provides for an obligee completion option.
3. The documents.
There
are a number of documents that may result when an obligee completes the
performance of the work through its own completion contractor, primarily
depending upon whether and/or when the obligee reaches an agreement with the
surety. If the obligee and the surety
agree up front that the obligee will complete the performance of the work with its
own completion contractor, there may be an agreement (interim, partial or
overall) with the surety to fund that completion, either over time as the work
progresses or at the end of the project when the final excess cost to complete
the performance of the work is known.
Under such circumstances, the surety will require a complete release and
discharge of its performance bond upon final payment to the obligee of the
excess cost of completion and any other agreed upon obligee claims.
If
the obligee and the surety agree to the surety’s “buying back” of its
performance bond, the surety, upon paying the obligee the agreed upon amount,
will receive a complete release and discharge of its performance bond and a
return of its original performance bond.
If
the obligee and the surety cannot reach an agreement resulting in a final
payment and the release and discharge of the surety’s performance bond, the
“last document” may be a complaint in a lawsuit for damages filed by the
obligee against the surety under the performance bond (which will generate more
documents).
4. The critical issues.
Probably
the most critical issue when the obligee completes the performance of the work,
with or without the surety’s consent, is the parties’ mitigation of their
damages. Both the obligee and the surety
must assess their risks and exposure whether the obligee either unilaterally
decides to move forward to complete the construction contract with its own
completion contractor and make a claim against the surety’s performance bond,
or the surety, by its actions and/or pursuant to the terms of the performance
bond, allows the obligee to complete the performance of the work on its own.
F. The Surety’s Denial of Liability Under the Performance Bond
A
surety may deny liability under the performance bond for a number of reasons as
discussed previously in this paper, including but not limited to the surety’s
assertion of the principal’s defenses (see
Section III. A.) and the surety’s assertion of its own defenses (see Section III. B.). The prior sections of this paper should be
reviewed for the basis of the surety’s denial of liability under the
performance bond.
1. The provisions of the performance bond.
a. AIA Document A311 Performance Bond.
While
the AIA Document A311 Performance Bond does not have a specific provision
authorizing a surety to deny liability, it does provide as a condition
precedent that the obligee must perform the obligee’s obligations under the
construction contract [“the Owner having performed Owner’s obligations” (under
the Contract)]. If, during its
investigation, the surety determines that there are defenses to the obligee’s
performance bond claim that form the basis for the surety’s denial of liability
under the performance bond, the surety may take the position that the obligee
has not complied with one of the necessary conditions precedent to make a claim
against the performance bond.[87]
b. Pursuant to the AIA Document A312
Performance Bond, the surety may:
4.4 Waive
its right to perform and complete, arrange for completion, or obtain a new
contractor and with reasonable promptness under the circumstances:
.2 Deny
liability in whole or in part and notify the Owner citing reasons therefor.
Obviously, the AIA Document A312 Performance
Bond provides the surety with the option and ability to deny liability under
the appropriate circumstances.
To the extent that the surety believes it
has defenses to the obligee’s claim against the performance bond, and the
performance bond does not specifically compel the surety to take one or more
specific actions, the surety may deny liability based upon its defenses.
2. The documents.
If
the surety denies liability to the obligee under the performance bond, it
should notify the obligee of its denial of liability. The AIA Document A312 Performance Bond
requires the surety to provide the obligee with its reasons for denying
liability.[88] Since it is very conceivable that the obligee
will eventually make a claim against whatever performance bond has been
executed, the surety may want to carefully set out in as much detail as
possible in writing why it is denying liability for the obligee’s claim under
the performance bond (with the surety’s denial letter obviously becoming an
exhibit in any future litigation).
3. The critical issues.
The
surety’s critical issue is whether its analysis of the facts gathered during
its investigation and its legal arguments are sufficient to justify the
surety’s denial of liability to the obligee under the performance bond. Whether the surety is relying on the
principal’s defenses or surety’s defenses, the facts and legal support for the
surety’s position may well end up in litigation over the obligee’s claim
against the performance bond.
G. The Surety’s Failure to Perform Under the Performance Bond
1. Introduction.
Other
than the surety’s denial of liability to the obligee under the performance bond
(which is a surety performance option under the AIA Document A312 Performance
Bond), it is extremely rare, if ever, that a surety would fail to perform under
the relevant performance bond and completely ignore its obligations. If the performance bond is an indemnity bond,
the surety is not expected to “perform” until the obligee makes a claim for its
damages with the expectation that the surety will reimburse the obligee for any
costs incurred over and above the balance of the contract price in performing
the remaining work and the obligee’s other direct or consequential
damages. If the performance bond
provides the surety with a number of performance options, then the surety’s
failure to exercise any one of those options may become the surety’s failure to
perform under the performance bond.
2. The provisions of the performance bond.
a. AIA Document A311 Performance Bond.
The
AIA Document A311 Performance Bond does not address the issue of the surety’s
failure to perform under the performance bond.
If the surety abrogates its performance obligations, the obligee may
make a claim against the surety.
b. AIA
Document A312 Performance Bond.
The
AIA Document A312 Performance Bond sets out five performance bond options for
the surety in paragraph 4, and then provides in paragraph 5 for what occurs if
the surety does not proceed with “reasonable promptness” as provided in
paragraph 4.[89] The obligee, upon providing notice to the
surety as required under paragraph 5,[90]
may declare the surety in default under the performance bond and may proceed to
enforce any remedies available to it.
3. The obligee’s claims for the surety’s
failure to perform.
If
the surety fails to perform under the performance bond, the obligee may have
claims against the surety’s performance bond and may assert those claims for
any damages that the obligee may claim or incur (see Section V. infra).
V. THE
SURETY’S LIABILITIES UNDER THE PERFORMANCE BOND
Regardless
of the surety’s choice of its performance bond option or options, and assuming
that the surety does not have a complete defense to the obligee’s performance
bond claim (either the principal’s defenses or the surety’s defenses), the
surety may have liability to the obligee under the performance bond. The surety’s position is that regardless of
the type of the obligee’s claims, the surety’s liability is capped at the penal
sum of the performance bond.
The
surety’s choice of its performance bond option may totally answer the question
of its liability under the performance bond.
For example, if the surety tenders a completion contractor to the
obligee, if the obligee completes the performance of the work under an
agreement with the surety that establishes the obligee’s damages for the excess
costs of the completion of the performance of the work, or the surety “buys
back” its performance bond, the surety will normally receive a release and
discharge of any further liability under the performance bond, including a
release from any other alleged obligee claims or damages. However, if the surety takes over the
completion of the performance of the work or finances its principal to complete
the performance of the work, the surety rarely, if ever, obtains such a release
and discharge of any other obligee claims against the performance bond.
Most performance bonds provide that only the
obligee may make a claim against the surety under the performance bond.[91] However, that has not prevented claims being
made against the surety’s performance bond by someone other than the obligee,
including third-party beneficiary claims (suppliers and subcontractors),
co-prime contractor claims, owner claims around a general contractor against a
subcontractor’s performance bond, adjacent property and/or business owner
claims, successor owner claims and personal injury/wrongful death claims (or
other claims due to the principal’s alleged negligent acts). [92] Other entities claiming through the obligee
may make a claim against the surety’s performance bond, including the obligee’s
assignees[93]
and other claimants alleging that they are subrogated to the obligee’s rights
under the surety’s performance bond.[94]
A. The Performance Bond Forms
1.
AIA Document A311 Performance
Bond.
Pursuant
to one option under the AIA Document A311 Performance Bond, the surety’s
liability is capped at the penal sum of the performance bond (with the surety’s
liability “not exceeding, including other costs and damages for which the
Surety may be liable hereunder” - namely the penal sum of the performance
bond).[95]
2. AIA Document A312 Performance Bond.
The AIA Document A312 Performance Bond provides in
paragraph 6:
After the
Owner has terminated the Contractor’s right to complete the Construction
Contract, and if the Surety elects to act under Subparagraph 4.1, 4.2, or 4.3
above, then the responsibilities of the Surety to the Owner shall not be
greater than those of the Contractor under the Construction Contract, and the
responsibilities of the Owner to the Surety shall not be greater than those of
the Owner under the Construction Contract.
To the limit of the amount of this Bond, but subject to commitment by
the Owner of the Balance of the Contract Price to mitigation of costs and
damages on the Construction Contract, the Surety is obligated without
duplication for:
6.1 The responsibilities of the Contractor
for correction of defective work and completion of the Construction Contract;
6.2 Additional legal, design professional and
delay costs resulting from the Contractor’s default, and resulting from the
actions or failure to act of the Surety under Paragraph 4; and
6.3 Liquidated
damages, or if no liquidated damages are specified in the Construction
Contract, actual damages caused by delayed performance or non-performance of
the Contractor.
The AIA Document
A312 Performance Bond, however, does set some limits on the surety’s potential
damages other than the limit set by the penal sum of the performance bond.[96]
B. The Obligee’s Claims for Damages
There
are a number of books, articles and papers that discuss the obligee’s claims
for damages under the surety’s performance bond, and some of the most relevant
and helpful are listed in the footnote below.[97] The obligee’s success or failure in
recovering damages from the surety’s performance bond depends on the damages for
which the surety has agreed to be responsible as defined by the performance
bond and the construction contract, if the construction contract has been
incorporated into the performance bond.
In the absence of any language limiting the surety’s exposure under
either the performance bond or the construction contract, the surety’s
liability is co-extensive with that of its principal; and the surety may be
liable to the obligee for certain direct and consequential damages for which
the principal is responsible due to the principal’s breach of the construction
contract. The following are the kinds of
claims and damages that obligees have alleged against the surety’s performance
bond.
1. The principal’s incomplete performance.[98]
2. The principal’s defective performance
(warranty claims and latent defect claims).[99]
3. The principal’s delay.
a. Liquidated damages. [100]
b. Actual delay damages (financing costs,
loss of use damages, overhead and other miscellaneous expenses).[101]
4. The principal’s negligence and lack of
liability insurance.[102]
5. Design-build contracts.[103]
6. Attorneys’ fees.[104]
7. Interest.[105]
C. Extra-Contractual Damages
If
the surety denies liability to the obligee under the performance bond (or if
the surety fails to perform under the performance bond), and it is later
alleged that the surety was incorrect in its decision, some obligees have
contended that the surety may be liable for extra-contractual damages that may
exceed the penal sum of the performance bond.
Not all courts will expand a breach of contract claim into a tort claim
against the surety.[106] Other jurisdictions have ruled differently.[107] There are a number of books, articles and
papers that discuss the obligee’s claim for extra-contractual damages against
the surety, and some of the most relevant and helpful are listed in the
footnote below.[108]
VI. OTHER SURETY ISSUES ARISING FROM A
PERFORMANCE BOND CLAIM
There
are a number of other issues that relate to a surety’s rights and obligations
arising from an obligee’s performance bond claim. While it is beyond the scope of this paper to
delve into these issues in any great detail, there are a number of books,
articles and papers that discuss the issues, and some of the most relevant and
helpful will be noted in footnotes below with respect to each issue.
A. The Surety’s Rights to the Contract Funds
As
discussed above, most performance bonds require the obligee to agree to pay the
“balance of the contract price” to the surety as a condition precedent to the surety’s
performance obligation under the performance bond. The “balance of the contract price” may also
include the terminated principal’s contract claims that it may have against the
obligee, which the obligee may dispute.
Regardless of whether the “balance of the contract price” includes the
remaining contract funds acknowledged by the obligee (the progress payments,
agreed extras and change orders, and retainage) or includes the principal’s
contract claims that have not been acknowledged or agreed to by the obligee,[109]
the surety will claim its rights to all of the remaining contract funds,
however characterized, based upon any rights that the surety may have,
including its subrogation rights and/or its secured creditor rights.
The
surety will make claims to the “balance of the contract price” for all of the
bonded contracts. However, the obligee,
the principal, and the universe of payment bond claimants, assignee banks and
lenders, trustees in bankruptcy and/or debtors-in-possession, taxing
authorities and other general creditors of the principal, including judgment
creditors, may assert a claim to the contract funds remaining under the
construction contract. The surety will
assert its rights to the remaining contract funds held by the obligee and may
have to compete against the other claimants for those contract funds.[110]
B. The Surety’s Rights Against the Principal and Indemnitors
Under the Indemnity Agreement
Sureties
require their principals and third-party indemnitors to execute an indemnity
agreement prior to the surety’s execution, with the principal, of any
performance and payment bonds. The
indemnity agreement sets out the principal’s and the indemnitor’s duties and
obligations to the surety and the surety’s rights, including enforcement
rights, against them under the indemnity agreement. During its investigation of the obligee’s
performance bond claim, the surety will take steps to preserve, maintain and
enforce its rights against the principal and the indemnitors under the
indemnity agreement.[111]
C. The Surety’s Rights Against Third Parties
In
addition to its rights against the obligee, the principal and the indemnitors,
the surety may have rights and claims against various third parties whose
actions or failure to act may increase the surety’s loss. The surety’s claims may be against
professionals and others who have provided services or materials to the obligee
or the principal, including accounting professionals, design professionals
(architects and engineers), lending and other financing institutions, and the
principal’s subcontractors and suppliers.
Furthermore, the surety may pursue claims under the principal’s
insurance policies as a source of recovery for its loss. Finally, to the extent that the principal
and/or the indemnitors have fraudulently or preferentially transferred their
assets to third parties, the surety may take action to recover those assets to
reduce the surety’s loss. There are a
number of books, articles and papers that discuss these issues in more detail.[112]
D. Alternative Dispute Resolution and Performance Bond Claims
Some
performance bonds provide the location (jurisdiction) where any proceeding may
be brought against the surety under the performance bond.[113] Many other performance bonds are silent on
the issue. With respect to any
alternative dispute resolution proceedings (mediation, arbitration and others),
few, if any, performance bonds directly provide for such actions in favor of or
against the surety. However, most
performance bonds incorporate the construction contract by reference into the
performance bond, and many construction contracts have alternative dispute
resolution provisions. The question
remains: is the surety bound by the
alternative dispute resolution provision in the construction contract and
required to participate in such a proceeding?
There are a number of books, articles and papers that discuss the
surety’s obligation or lack of obligation to participate in an alternative
dispute resolution proceeding between the obligee and the principal under the
construction contract.[114]
E. The Principal’s Bankruptcy and its Effects on an Obligee’s
Performance Bond Claim
The
principal’s filing of a bankruptcy proceeding will affect both the obligee’s
rights under the construction contract and the surety’s performance bond and
the surety’s responses to the obligee’s performance bond claim. This complex discussion has been discussed in
a number of books, articles and papers[115]
and is beyond the scope of this paper.
VIII. SUMMARY AND CONCLUSION
There
is no participant in the construction process who is happy when the obligee or
the principal believes that the other party has materially breached the
construction contract to the extent that they are entitled to terminate the
other party for default. Whether or not
the construction contract has a surety performance bond, the termination for
default will effect everyone coming into contact with the construction project,
including specifically the obligee, its lender and other related parties as
well as the principal, its subcontractors and suppliers and other related
parties. When a surety performance bond
is available, the surety’s performance bond lifeboat may be called upon for
assistance during the storm of broken relationships and expectations. In a very short period of time, the surety
is requested to bail out the obligee’s boat and/or salvage the wreck of the
construction project. There are many
issues that must be addressed, whether before, during or after the surety’s
rescue efforts. Hopefully, this paper,
like the guiding light of a lighthouse and the comforting sounds of the foghorn
and buoy bell, will assist the parties to the construction process in
successfully using the surety performance bond lifeboat.
APPENDIX
BIBLIOGRAPHY
OF FREQUENTLY CITED SECONDARY MATERIALS
Managing and Litigating the Complex Surety Case, 2d Ed. (Philip L. Bruner and Tracey L. Haley, eds. 2007), Tort Trial and Insurance Practice Section, American Bar Association.
Chapter 1 - Strategic “Generalship” of the Complex Construction Suretyship Case by Philip L. Bruner and Tracey L. Haley.
Chapter 3 - Deciding to Litigate: The Surety’s Recourse Against its Principal and Indemnitors by Armen Shahinian, Marc Brown and Joseph Monaghan.
Chapter 4 - Deciding to Litigate: The Surety’s Recourse Against Third Parties by Ronald F. Goetsch and Christopher R. Ward.
Chapter 5 - Deciding to Litigate: The Surety’s Rights Against Property and Liability Insurers of the Obligee, Principal, and Subcontractors by Patrick J. O’Connor, Jr.
Performance
Bond Manual (
Bond
Default Manual, 3d Ed. (Duncan L. Clore, Richard E. Towle and
Michael J. Sugar, Jr., eds. 2005), Tort
Trial and Insurance Practice Section, American Bar Association.
Chapter 2, Section A - The Surety’s Investigation by William S. Piper and Carl C. Coe, Jr.
Chapter 3 - The Surety’s Analysis of Investigative Results: “To Perform or Not to Perform - That is the Question” by Philip L. Bruner, Patrick J. O’Connor, Jr. and Tracy L. Haley
Chapter 4 - Financing the Principal by George J. Bachrach and Matthew L. Silverstein.
Chapter 5 - Takeover and Completion by Gregory L. Daily and Todd C. Kazlow.
Chapter 6 - Tender by E.A. “Seth” Mills, Jr. and Susan M. Moore.
Chapter 7 - Completion by the Bond Obligee by Deborah S. Griffin and Stephen J. Beatty.
Chapter 8 - Public Works Projects by Donald G. Gavin, Shannon J. Briglia and Mark S. Marino.
Chapter 11 - Considerations With Respect to Insurance Coverage by Christopher R. Ward and Mary Jean Pethick.
The
Surety’s Indemnity Agreement - Law & Practice (Marilyn Klinger,
Gary Judd and George J. Bachrach, eds. 2002), Tort
Trial and Insurance Practice Section, American Bar Association.
The Law of Suretyship, 2d Ed. (Edward G. Gallagher, ed. 2000), Tort and Insurance Practice Section, American Bar Association.
Chapter 6 - Contract Performance Bonds by Marilyn Klinger, James P. Diwik and Kevin L. Lybeck.
Chapter 7 - Discharge of the Performance Bond Surety by M. Michael Egan and Marla Eastwood.
Chapter 21 - Arbitration of Performance Bond Disputes by H. Bruce Shreves and Kevin L. Lybeck.
The
Law of Performance Bonds (
Chapter 2 - Default, Notice of Default, Impact Upon Surety’s Obligations Where Notice is Not Given by Benjamin D. Lentz.
Chapter 3 - Rights of Surety in Event of Default by James J. Mercier and John T. Harris.
Chapter 4 - Entitlement to Contract Proceeds by Edward G. Gallagher.
Chapter 6 - Liability of the Performance Bond Surety (Under Contract of Suretyship) by John H. Gregory and Michael Jay Rune, II.
Chapter 9 - Defenses Available to the Surety by Julia Blackwell Gelinas.
Chapter 11 - Effect of an Arbitration Provision in the Principal’s Contract with the Obligee by James D. Ferrucci.
Salvage
by the Surety (George J. Bachrach, ed. 1998), Tort and Insurance Practice Section, American
Bar Association.
Chapter 1 - The Surety’s Rights to Obtain Salvage - Exoneration, Reimbursement, Subrogation and Contribution by George J. Bachrach.
Chapter 3 - The Principal’s Contract Claims as Salvage - A Primer by Patrick J. O’Connor, Jr.
Chapter 5 - The Surety’s Claims Against Third Parties by James D. Ferrucci and Scott D. Baron.
1729159v2
[1] Sureties
write performance and payment bonds on behalf of their general contractor
customers, as principals, to the owners, as obligees, and on behalf of their
subcontractor customers, as principals, to the general contractors, as
obligees. There are some major
differences between the circumstances when an owner default terminates a
general contractor and makes a claim against the surety’s performance bond and
when a general contractor default terminates a subcontractor and makes a claim
against the surety’s subcontractor performance bond. To eliminate what might create some
confusion, this paper will always address the owner (or general contractor) as
the “obligee” under the performance bond and the general contractor (or
subcontractor) as the “principal” under
the performance bond, as appropriate. In
the instances when this paper may make specific points and observations about
the general contractor and subcontractor relationship, the general contractor,
as “obligee,” and the subcontractor, as “principal.” will be specifically
identified.
[2] Stewart R. Duke & Mary Jeanne
Anderson, How
Contract Surety Bonds Are Underwritten, in The
Law of Suretyship, 2d Ed. 49-61 (Edward G. Gallagher, ed. 2000); Lynn M. Schubert, Why Obligees Buy Bonds, in
The Law of Suretyship, 2d Ed. 41-47 (Edward
G. Gallagher, ed. 2000); Roger P.
Sauer, Creation of the Relationship, in The Law of Performance Bonds 1-17
(Lawrence R. Moelmann & John T. Harris, eds. 2000); and Marilyn Klinger, A
Toast - To the Underwriters: The
Underwriting Process and Salvage by the Surety, in Salvage by the Surety 63-92 (George J. Bachrach, ed. 1998).
[3] “A surety, by providing bonds to
its principal, is, in reality, providing the surety’s credit to the principal
in order for the principal to enter into a contract with the obligee. In banking parlance, the surety’s bonding of
its principal creates a “credit facility” where the surety, for a fee, extends
its credit to the principal. The surety
expects to incur no loss as a result of that extension of credit. The surety’s extension of credit is done with
the understanding, whether under common law or through a written agreement such
as an agreement of indemnity, that the principal, and any third-party
indemnitors, will reimburse the surety in the event that the surety incurs a
loss under the bonds it executes for the principal.” George J. Bachrach, The Surety’s Rights to Obtain Salvage - Exoneration, Reimbursement,
Subrogation and Contribution, in Salvage
by the Surety 1 (George J. Bachrach, ed. 1998).
[4] There are
many basic types of performance bonds, including but not limited to standard
form private performance bonds, statutorily required performance bonds,
indemnity bonds, manuscript bonds, completion bonds, and others that an obligee
may request or require and a principal and a surety may execute. The various types of performance bonds are
discussed in Philip L. Bruner, Patrick J. O’Connor, Jr. & Tracey L. Haley, The Surety’s Analysis of Investigative
Results: “To Perform or Not to Perform -
That is the Question,” in Bond
Default Manual, 3d Ed. 87-93 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005).
Occasionally, the “standard” performance bond may become a “manuscript”
performance bond that shifts the “normal construction risks and liabilities” in
some fashion such that it may become “onerous” to one party (usually the
surety) or another. Steven D. Nelson, “Onerous” Bond Forms - A Look at Departures
from Standard Performance and Payment Bond Provisions (unpublished paper
submitted at the ABA Forum on the Construction Industry/TIPS Fidelity &
Surety Law Committee annual midwinter meeting on January 29, 2004).
[5] There
are times when there are “dual obligees”on the performance bond. Frequently, the obligee may be the owner of
the construction project and the dual obligee is the owner’s financing lender. Another dual obligee situation may be the obligee
general contractor and the dual obligee owner on a subcontractor performance
bond. See Section V., note 91, infra.
[6] Once a claim arises, the surety
has a duty to independently investigate the claim. Dodge
v. Fid. & Deposit Co. of Md., 778 P.2d 1240 (
[7] For a concise yet compelling
discussion of the astounding myriad and variety of legal and other
relationships on a construction project, see
Philip L. Bruner & Tracey L. Haley,
Strategic “Generalship” of the Complex Construction Suretyship Case, in Managing and Litigating the Complex Surety
Case, 2d Ed. 1-9 (Philip L. Bruner & Tracey L. Haley, eds.
2007).
[8] The “classic dilemma”
for a surety is when both the obligee and the principal are adamant that their
positions are correct, with the obligee declaring the principal to be in
default under the construction contract and asserting a claim against the
surety under the performance bond and the principal claiming that the default
was wrongful such that the obligee is in breach of contract and the surety has
no obligation to perform. See Marilyn Klinger, James P. Diwik
& Kevin L. Lybeck, Contract
Performance Bonds, in The Law of
Suretyship, 2d Ed. 94-96 (Edward G. Gallagher, ed. 2000); John W.
Hinchey, Surety’s Performance Over
Protest of Principal: Considerations and
Risks, 22 Tort & Ins. L.J.
133 (1986).
[9] See AIA A312 Performance Bond, paragraph
4.4.1, for the only reference in that performance bond to a surety’s
“investigation”.
[10] While
the “when” of a surety’s investigation may be unknown and/or unsettled, the
right of a surety to perform an investigation is not. See
Seaboard Sur. Co. v. Town of Greenfield, 266 F. Supp. 2d 189, 194 (D. Mass.
2003), aff’d, 370 F.3d 215 (1st
Cir. 2004) (“courts have deemed that it is commercially reasonable to allow the
sureties time to investigate the circumstances surrounding a default
termination of a contractor before selecting from the various performance
options available to them.”).
[11] See
Section III. B. 2., infra.
[12] The
AIA Document A312 Performance Bond (1984) defines Owner Default as:
12.4
Owner Default: Failure of the
Owner, which has neither been remedied nor waived, to pay the Contractor as
required by the Construction Contract or to perform and complete or comply with
the other terms thereof.
[13] See
Section III. B. 2., infra.
[14] The
AIA Document A312 Performance Bond (1984) defines Contractor Default as:
12.3
Contractor Default: Failure of
the Contractor, which has neither been remedied nor waived, to perform or
otherwise to comply with the terms of the Construction Contract.
[15] The
AIA Document A312 Performance Bond (1984) defines the Construction Contract as:
12.2
Construction Contract: The
agreement between the Owner and the Contractor identified on the signature
page, including all Contract Documents and changes thereto.
[16] The
AIA Document A312 Performance Bond (1984) defines the Balance of the Contract
Price as:
12.1
Balance of the Contract Price:
The total amount payable by the Owner to the Contractor under the
Construction Contract after all proper adjustments have been made, including
allowance to the Contractor of any amounts received or to be received by the
Owner in settlement of insurance or other claims for damages to which the
Contractor is entitled, reduced by all valid and proper payments made to or on
behalf of the Contractor under the Construction Contract.
[17] William S.
Piper & Carl C. Coe, Jr., The
Surety’s Investigation, in Bond
Default Manual, 3d Ed. 43-60 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005) (which focuses on the objectives of the
investigation, the responsibility to investigate, the information required to
make appropriate decisions, the significance of such information, and the
source from which such information is obtainable); Marilyn Klinger, James P.
Diwik & Kevin L. Lybeck, Contract
Performance Bonds, in The Law of
Suretyship, 2d Ed. 96-98 (Edward G. Gallagher, ed. 2000); Ray H. Britt, The Surety’s Investigation, 17 Forum 1151 (1982).
[18] William S.
Piper & Carl C. Coe, Jr., The
Surety’s Investigation, in Bond
Default Manual, 3d Ed. 54-57 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005); Marilyn Klinger, James P. Diwik & Kevin
L. Lybeck, Contract Performance Bonds, in
The Law of Suretyship, 2d Ed. 96-98
(Edward G. Gallagher, ed. 2000); Ray H. Britt, The Surety’s Investigation, 17 Forum
1151 (1982).
[19] Most
surety underwriting and financial files do not contain a copy of the fully
executed performance and payment bonds.
The bond agent usually executes the bonds on behalf of the surety and
sends the bonds to the principal to execute and then to deliver the fully
executed bonds to the obligee with an executed copy of the construction
contract. As a result, the obligee is
frequently the only party that has a fully executed copy of the final performance
and payment bonds.
[20] The
primary issue for the surety’s initial investigation is whether the obligee is
justified in terminating the principal’s construction contract for default and
the factual and legal basis that may constitute and support a justified
contract termination. See note 24, infra.
[21] See Section III. B. 1. and 2., infra.
[22] The
principal’s performance or lack of performance of all of the material
obligations under the construction contract may affect the surety’s assertion
of the principal’s defenses. For
example, the principal may have an implied duty to seek clarification of
patently ambiguous design documents, an implied warranty of workmanship, an
implied duty of cooperation, an implied product warranty of merchantability and
fitness of purpose, an implied duty to warn, a duty to perform a site
inspection and/or an obligation to give timely claim notice and submissions in
order to fully comply with the terms of the construction contract. See Philip
L. Bruner & Tracey L. Haley, Strategic
“Generalship” of the Complex Construction Suretyship Case, in Managing and Litigating the Complex Surety
Case, 2d Ed. 54-63 (Philip L. Bruner & Tracey L. Haley, eds. 2007).
[23] Philip L.
Bruner & Tracey L. Haley, Strategic
“Generalship” of the Complex Construction Suretyship Case, in Managing and Litigating the Complex Surety
Case, 2d Ed. (Philip L. Bruner & Tracey L. Haley, eds. 2007)
(hereinafter “Bruner - Complex”); Philip L. Bruner, Patrick J. O’Connor, Jr.
& Tracey L. Haley, The Surety’s Analysis
of Investigative Results: “To Perform or
Not to Perform - That is the Question,” in Bond Default Manual, 3d Ed. (Duncan L. Clore, Richard E.
Towle & Michael J. Sugar, Jr., eds. 2005) (hereinafter “Bruner - Bond
Default”); M. Michael Egan & Marla Eastwood, Discharge of the Performance Bond Surety, in The Law of Suretyship, 2d
Ed. (Edward G. Gallagher, ed. 2000) (hereinafter “Egan - Suretyship”);
Julia Blackwell Gelinas, Defenses
Available to the Surety, in The Law
of Performance Bonds (Lawrence R. Moelmann & John T. Harris, eds.
2000) (hereinafter “Gelinas - Performance Bond”).
[24] An obligee’s wrongful termination of
the principal’s construction contract is itself a breach of that construction
contract that relieves the principal from its obligations under the
construction contract and the principal and the surety from their liability
under the performance bond. During its
investigation, the surety will attempt to determine what constitutes default
under the principal’s construction contract and whether the obligee’s
termination of the principal for default is proper and justified, or whether
the obligee wrongfully terminated the principal’s construction contract. There are a number of facts and factors that
are relevant for the issue of a wrongful termination, including the importance
of a good faith motive for the obligee’s termination, the importance of a
proper cure notice, and/or the obligee’s waiver of its right to terminate the
principal for default. See Bruner - Complex, pp. 16-28; Bruner
- Bond Default, pp. 93-112. Furthermore:
The
obligee’s termination of the principal under the termination clause of a bonded
contract can be upheld only if the obligee sustains its burden of proof that
(1) the principal materially and inexcusably breached its contract, (2) the
principal’s breaches were not induced or preceded by the obligee’s own
supervening material breaches of contract, such as nonpayment,
maladministration of the construction process, or refusal to grant proper time
extensions or other recognized “contract defenses,” (3) the obligee’s
termination was not improperly motivated or conceived in bad faith and was made
independently and with the exercise of discretion by its representative having
authority to terminate the contract, (4) the principal was given ample notice
of deficiencies so as to understand what needed to be “cured,” and (5) the
obligee properly followed its contractually-specified termination
procedure.
Bruner - Bond Default, p. 104; see also Bruner - Complex, pp. 20-21;
Gelinas - Performance Bond, pp. 205-06.
The obligee’s wrongful termination of the principal’s construction
contract may lead to the obligee’s release and discharge of the surety’s
principal and the surety and/or the obligee’s failure to comply with the
performance bond’s conditions precedent requiring the surety to perform. See
Section III. B. 1. and 2., infra.
[25] Bruner
- Complex, pp. 46-47; Bruner - Bond Default, pp. 128-29; Egan - Suretyship, pp.
138-39; T. Scott Leo & B. Scott Douglass, The Obligee’s Duties to Provide Plans and Specifications, Make Payment,
and Process Change Orders (unpublished paper submitted at the ABA/TIPS
Fidelity and Surety Law Committee annual midwinter meeting on January 24,
1997).
[26] Bruner
- Complex, pp. 34-42; Bruner - Bond Default, pp. 117-25; Gelinas - Performance
Bond, pp. 202-03; T. Scott Leo & B. Scott Douglass, The Obligee’s Duties to Provide Plans and Specifications, Make Payment,
and Process Change Orders (unpublished paper submitted at the ABA/TIPS
Fidelity and Surety Law Committee annual midwinter meeting on January 24,
1997).
[27] Bruner
- Complex, pp. 36-37 and its footnotes 103-05; Bruner - Bond Default, pp.
119-20.
[28] Bruner
- Complex, pp. 42-44; Bruner - Bond
Default, pp. 125-26.
[29] Bruner
- Complex, p. 50; Bruner - Bond Default, p. 132; Gelinas - Performance Bond,
pp. 204-05; Restatement (2d) of the Law of Contracts § 261 (1981).
[30] Bruner
- Complex, pp. 45-49; Bruner - Bond Default, pp. 127-32; Egan - Suretyship, pp.
138-39; Gelinas - Performance Bond, p. 203; T. Scott Leo & B. Scott
Douglass, The Obligee’s Duties to Provide
Plans and Specifications, Make Payment, and Process Change Orders (unpublished
paper submitted at the ABA/TIPS Fidelity and Surety Law Committee annual
midwinter meeting on January 24, 1997).
[31] Bruner
- Complex, pp. 23-27; Bruner - Bond Default, pp. 107-10; Gelinas - Performance
Bond, pp. 206-07.
[32] Bruner
- Complex, pp. 50-51; Bruner - Bond Default, p. 133; see Bruner & O’Connor on
Construction Law, § 18:17-18:20.
[33] Bruner
- Complex, pp. 51-52; Bruner - Bond Default, pp. 133-34.
[34] Bruner
- Complex, pp. 53-54; Bruner - Bond Default, pp. 135-36; Gelinas - Performance
Bond, pp. 219-20; Restatement (Third) of
Suretyship and Guaranty § 39 (1996).
[35] Gelinas
- Performance Bond, p. 207.
[36] See Section III. A. 1. and note 24, supra; Restatement
(Third) of Suretyship and Guaranty § 39 (1996) (the obligee’s release of
the principal from its duties and obligations pursuant to the underlying
construction contract releases the surety’s obligations under the bond).
[37] Philip L.
Bruner & Tracey L. Haley, Strategic
“Generalship” of the Complex Construction Suretyship Case, in Managing and Litigating the Complex Surety
Case, 2d Ed. 16-28 (Philip L. Bruner & Tracey L. Haley, eds. 2007);
Philip L. Bruner, Patrick J. O’Connor, Jr. & Tracey L. Haley, The Surety’s Analysis of Investigative
Results: “To Perform or Not to Perform -
That is the Question,” in Bond
Default Manual, 3d Ed. 93-112 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005); Benjamin D. Lentz, Default, Notice of Default, Impact Upon Surety’s Obligations Where
Notice is Not Given, in The Law of
Performance Bonds pp. 19-35 (Lawrence R. Moelmann & John T. Harris,
eds. 2000); see also note 24, supra, for a discussion concerning the
obligee’s wrongful termination of the principal’s construction contract.
[38] In
L&A Contracting Company v. Southern
Concrete Services, Inc., 17 F.3d 106, 110 (5th Cir. 1994), the
court articulated the distinction between a breach and a default as
follows:
Although the terms breach and default are
sometimes used interchangeably, their meanings are distinct in construction
suretyship law. Not every breach of a construction
contract constitutes a default sufficient to require the surety to step in and
remedy it. To constitute a legal
default, there must be (1) material breach or series of material breaches (2)
of such magnitude that the obligee is justified in terminating the
contract. Usually the principal is
unable to complete the project, leaving termination of the contract the
obligee’s only option.
[39] While
there are a number of definitions in the case law of “materiality” or “material
breach,” the Restatement (2d) of
Contracts § 241 provides:
1. The
extent to which the injured party will be deprived of the benefit which he
reasonably expected;
2. The
extent to which the injured party can be adequately compensated for the part of
that benefit of which he will be deprived;
3. The
extent to which the party failing to perform (or failing to offer to perform)
will suffer forfeiture;
4. The
likelihood that the party failing to perform (or failing to offer to perform)
will cure his failure, taking account of all of the circumstances including any
reasonable assurances; and
5. The
extent to which the behavior of the party failing to perform or to offer to
perform comports with standards of good faith and fair dealing.
[40] The
question is whether the default provisions in a construction contract are
“exclusive” or “non-exclusive.”
Specifically, if the construction contract default provision is silent
on whether it is exclusive or not, may the obligee assert a basis or ground for
default that is not described in the construction contract? In Olin
Corporation v. Central Industries, Inc., 576 F.2d 642 (5th Cir.
1978), the court noted the split in
authority between (1) what the court referred to as the “Corbin view” [6
Richard Corbin Contracts § 1266
at 64 (1962)], namely that “where such a termination provision is included in a
contract, it constitutes the exclusive means of terminating the contract, and
(2) what the court referred to as the “Williston view” [Samuel Williston, Willison on Contracts, § 842, note 1 at
165 (3d ed. 1959)], namely that “[U]nless a contract provision for termination
for breach is in terms exclusive (citation omitted), it is a cumulative remedy
and does not bar the ordinary remedy of termination for a ‘breach which is
material, or which goes to the root of the matter or essence of the contract.’”
[41] Even
if the obligee has grounds for asserting that the principal is in default under
the construction contract, the obligee may waive, by its actions or words, the
right to declare the principal in default.
See Bruner - Complex, pp. 50-51; Bruner - Bond Default, p. 133.
[42] Numerous
cases have held that the notice to the surety must be stated in clear, direct,
definite, explicit, unambiguous and unequivocal language. See
Seaboard Sur. Co. v. Town of Greenfield, 266
F. Supp. 2d 189 (D. Mass. 2003), aff’d,
370 F.3d 215, 223 (1st Cir. 2004)
[citing L&A Contracting Co. v. Southern Concrete Services, Inc., 17
F.3d 106, 111 (5th Cir. 1994)
(“A declaration of default sufficient to invoke
the surety’s obligations under the bond must be made in clear, direct,
and unequivocal language. The
declaration must inform the surety that the principal has committed a material
breach or series of material breaches of the subcontract, that the obligee
regards the subcontract as terminated, and that the surety must immediately
commence performing under the terms of its bond.”); Elm Haven Constr. Ltd. P’ship v. Neri Constr. LLC., 281 F. Supp. 2d
406 (D. Conn. 2003), aff’d, 376 F.3d
96 (2d Cir. 2004); and Balfour Beatty
Constr., Inc. v. Colonial Ornamental Iron Works, Inc., 986 F. Supp. 82, 86
(D. Conn. 1997)]; Enterprise Capital,
Inc. v. San-Gra Corp., 284 F. Supp. 2d 166 (D. Mass. 2003).
[43] A
number of cases hold that the surety is entitled to the obligee’s notice of a
declaration of a principal’s default either under the performance bond or under
the construction contract. L&A Contracting Co. v. Southern Concrete
Services, Inc., 17 F.3d 106 (5th Cir. 1994) (the court found that the
performance bond required a formal declaration of default as a condition
precedent to the surety’s liability. The
court held that the obligee’s failure to send the surety any notice of default resulted in a complete
discharge of the surety’s performance bond obligations); Dragon Construction, Inc. v. Parkway Bank & Trust, 678 N.E.2d
55 (Ill. App. Ct. 1997) (the court held that a performance bond was null and
void when the obligee failed to provide seven days’ notice to the surety and
the principal as required, not under the performance bond, but under the
general conditions of the construction contract that was incorporated into the
performance bond); Enterprise Capital,
Inc. v. San-Gra Corp., 284 F. Supp. 2d 166 (D. Mass. 2003); Balfour Beatty Constr., Inc. v. Colonial
Ornamental Iron Works, Inc., 986 F. Supp. 82 (D. Conn. 1997).
[44] Siegfried Construction, Inc. v. Gulf
Insurance Company, 203 F.3d 822 (4th Cir. 2000) (where no formal
declaration of default or termination of the construction contract was required
under Virginia law to trigger a surety’s performance bond obligations); Walter Concrete Constr. Corp. v. Lederle Lab.,
788 N.E.2d 609, 610 (N.Y. 2003) (“Notwithstanding [the surety’s] contrary
claim, the AIA-311 performance bond contains no explicit provision requiring a
notice of default as a condition precedent to any legal action on the bond . .
. Unlike the AIA-312 bond, another industry standardized bond, an action on the
AIA-311 bond is not tied to a declaration of default, the principal’s cessation
of work or the surety’s refusal to perform under the bond.”); Winston Corporation v. Continental Casualty
Co., 361 F. Supp. 1023, rev’d,
508 F.2d 1298 (6th Cir. 1975).
[45] L&A Contracting Co. v. Southern Concrete
Services, Inc., 17 F.3d 106 (5th
Cir. 1994); Balfour Beatty Construction,
Inc. v. Colonial Ornamental Iron Works, Inc., 986 F. Supp. 82 (D.
[46] Winston Corporation v. Continental Casualty
Co., 361 F. Supp. 1023, rev’d,
508 F.2d 1298 (6th Cir. 1975) (the court found that the failure to
give a seven-day notice required by the general conditions of the contract was
an insubstantial breach that might permit the surety to a discharge to the
extent of the harm, but would not justify a complete discharge of the surety’s
obligations); Blackhawk Heating &
Plumbing Co. v. Seaboard Surety Co., 534 F. Supp. 309 (N.D. III. 1982) (a
failure by the obligee to give notice of a declaration of default might result
in a pro tanto rather than complete
discharge of the surety’s obligations under the performance bond); Plowden & Roberts, Inc. v. Conway,
192 So.2d 528, 533 (Fla. Dist. Ct. App. 1966) (the “surety’s liability is merely
reduced by any harm which it suffered by the fact that it was not accorded its
rights to remedy the default.”); Continental Bank & Trust Co. v. American
Bonding Co., 605 F.2d 1049 (8th Cir. 1979).
[47] Elm Haven Constr. Ltd. P’ship v. Neri
Constr. LLC, 281 F. Supp. 2d 406 (D. Conn. 2003), aff’d, 376 F.3d 96 (2d Cir. 2004); Balfour Beatty Constr.,Inc. v. Colonial Ornamental Iron Works, Inc.,
986 F. Supp. 82 (D. Conn. 1997); Enterprise
Capital, Inc. v. San-Gra Corp., 284 F. Supp. 2d 166 (D. Mass. 2003); Dragon Construction, Inc. v. Parkway Bank
& Trust, 678 N.E.2d 55 (Ill. App. Ct. 1997); Insurance Company of North America v.
[48] Bruner
- Complex, pp. 30-33; Bruner - Bond Default, pp. 113-17; see Bank of Brewton, Inc. v. Int’l Fid. Ins.
[49] Bruner
- Complex, pp. 47-49 & 63-64; Bruner - Bond Default, pp. 129-31 &
137-38; Egan - Suretyship, pp. 128-36; Gelinas - Performance Bond, pp. 210-13; Restatement (Third) of Suretyship and Guaranty
§ 41 (1996).
[50] Bruner
- Complex, pp. 67-69; Bruner - Bond Default, pp. 141-43; Egan - Suretyship, pp.
120-28; Gelinas - Performance Bond, pp. 214-15 & 217-19; Randall I. Marmor
& Gilbert J. Schroeder, Overpayment
of the Principal as a Defense to the Surety (unpublished paper submitted at
the ABA/TIPS Fidelity and Surety Law Committee annual midwinter meeting on
January 24, 1997); Restatement (Third)
of Suretyship and Guaranty § 42 (1996).
[51] Egan
- Suretyship, pp. 136-38; Gelinas - Performance Bond, p. 215; James A. Knox,
Jr., The Surety’s Extension of Time
Defense, 33 Tort & Ins. L.J.
891 (1998); Restatement (Third) of
Suretyship and Guaranty § 40(b) (1996).
[52] Bruner
- Complex, pp. 71-73; Bruner - Bond Default, pp. 144-45; Egan - Suretyship, pp.
136-38; Gelinas - Performance Bond, pp. 207-10.
[53] In
Ohio Casualty Insurance Company v. United
States, 12 Cl. Ct. 590 (1987), the surety alleged that the obligee violated
its equitable duty to the surety and abused its discretion in failing to
terminate the surety’s principal. The
court found that the obligee abused its discretion by failing to timely
terminate the principal. The court found
that the evidence “overwhelmingly showed a pattern of unreasonable conduct on
the part of those responsible for the administration of the contract,” 12 Cl.
Ct. at 591, and that “it would be manifestly unjust to make the surety pay for
the Navy’s mistake.”
[54] Gelinas
- Performance Bond, p. 214.
[55] Bruner
- Complex, pp. 64-67; Bruner - Bond Default, pp. 138-41; Egan - Suretyship, pp.
129-31; Gelinas - Performance Bond, pp. 213 & 216-17.
[56] Bruner
- Complex, pp. 73-76; Bruner - Bond Default, pp. 145-48; Egan - Suretyship, pp.
139-43.
[57] Bruner
- Complex, pp. 76-77 n.243, 246 [see Restatement (Third) of Suretyship &
Guaranty § 12. See also Ground Imp. Techniques, Inc. v.
Merchants Bonding Co., 63 F. Supp. 2d 1272 (D. Colo. 1999) (applying Restatement (Third) of Suretyship &
Guaranty and upholding the surety’s right to rescission upon proof that
its issuance of a bond to an excavation subcontractor on a Department of Energy
environment cleanup project was induced by concealment of material
information); see also Kvaerner Constr.,
Inc. v. Am. Safety Cas. Ins.
[58] The AIA
Document A311 Performance Bond provides the following performance options for
the surety:
. . . the Surety may
promptly remedy the default, or shall promptly
1) Complete the
Contract in accordance with its terms and conditions; or
2) Obtain a bid
or bids for completing the Contract in accordance with its terms and
conditions, and upon determination by Surety of the lowest responsible bidder,
or, if the Owner elects, upon determination by the Owner and the Surety jointly
of the lowest responsible bidder, arrange for a contract between such bidder
and Owner, and make available as Work progresses (even though there should be a
default or a succession of defaults under the contract or contracts of
completion arranged under this paragraph) sufficient funds to pay the cost of
completion less the balance of the contract price; but not exceeding, including
other costs and damages for which the Surety may be liable hereunder, the
amount set forth in the first paragraph hereof.
The term “balance of the contract price,” as used in this paragraph,
shall mean the total amount payable by Owner to Contractor under the Contract
and any amendments thereto, less the amount properly paid by Owner to
Contractor.
[59] The AIA
Document A312 Performance Bond provides the following performance options for
the surety:
4. When the
Owner has satisfied the conditions of Paragraph 3, the Surety shall promptly
and at the Surety’s expense take one of the following actions:
4.1 Arrange for
the Contractor, with consent of the Owner, to perform and complete the
Construction Contract; or
4.2 Undertake to
perform and complete the Construction Contract itself, through its agents or
through independent contractors; or
4.3 Obtain bids
or negotiated proposals from qualified contractors acceptable to the Owner for
a contract for performance and completion of the Construction Contract, arrange
for a contract to be prepared for execution by the Owner and the contractor
selected with the Owner’s concurrence, to be secured with performance and
payment bonds executed by a qualified surety equivalent to the bonds issued on
the Construction Contract, and pay to the Owner the amount of damages as
described in Paragraph 6 in excess of the Balance of the Contract Price
incurred by the Owner resulting from the Contractor’s default; or
4.4 Waive its
right to perform and complete, arrange for completion, or obtain a new
contractor and with reasonable promptness under the circumstances:
.1 After
investigation, determine the amount for which it may be liable to the Owner
and, as soon as practicable after the amount is determined, tender payment
therefor to the Owner; or
.2 Deny
liability in whole or in part and notify the Owner citing reasons therefor.
[60] See
note 4, supra. Under the Miller Act
performance bond, the surety’s obligation is void if the principal “performs
and fulfills all the undertakings, covenants, terms, conditions, and agreements
in the contract.” If the principal fails
to perform, the surety is bound “for payment of the penal sum” of the Miller
Act performance bond. Nothing is said
about and no performance bond options are provided for to describe how the
surety is to fulfill its performance obligations under the Miller Act
performance bond if the principal fails to fulfill its obligations under the
contract with the federal government.
Essentially, the Miller Act performance bond is an indemnity bond. See
Bruner - Bond Default, pp. 91-92. The
Federal Acquisition Regulations, 48 C.F.R. § 49.404, acknowledge that a “surety
has certain rights and interests in the completion of the contract work and the
application of any undisbursed funds,” and that “the contracting officer must
consider carefully the surety’s proposals for completing the contract.” § 49.404(b). Furthermore, the “contracting officer should
permit surety offers to complete the contract.” § 49.404(c). “There may be conflicting demands for the
defaulting contractor’s assets, including
unpaid prior earnings (retained percentages and unpaid progress
estimates). Therefore, the surety may
include a “takeover” agreement in its proposal, fixing the surety’s rights to
payment from those funds. The
contracting officer may (but not before the effective date of termination)
enter into a written agreement with the surety.
§ 49.404(d). In reality, the
federal government may consider any kind of an agreement with the surety to
complete the performance of the work, including a takeover agreement or a
tender agreement. Furthermore, a review
of the cases involving the federal government shows that the surety’s financing
of the principal has been used as a means for the surety’s performance of its
obligations under the Miller Act performance bond.
For additional secondary materials concerning the federal
government as the obligee under the surety’s performance bond, see Donald G. Gavin, Shannon J. Briglia
& Mark S. Marino, Public Works
Projects, in Bond Default Manual, 3d
Ed. 287-311 (Duncan L.
Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005); George J.
Bachrach & Robert F. Carney, The
Surety and the United States Court of Federal Claims - Revisited (unpublished
paper submitted at the Tenth Annual Northeast Surety and Fidelity Claims
Conference on October 21, 1999); George J. Bachrach & Robert F. Carney, The Surety and the United States Court of
Federal Claims (unpublished paper submitted at the Surety Claims Institute
annual meeting on June 22, 1995); and David D. Crane, A Critical Examination of the Federal Acquisition Regulations Related
to Sureties (unpublished paper submitted at the ABA annual meeting on
August 13, 1991).
[61] See Section IV. A. 5. c., infra.
[62] See Section VI. D., infra.
[63] Many
states have case law that holds that the provisions of the statute are read
into a statutory performance bond, that where the performance bond language
conflicts with the statutory requirements, it is simply disregarded, but that
if the performance bond language affords coverage greater than required by the
statute, then the surety’s liability will increase beyond that required by the
statute. See Bruner - Bond Default, pp. 90-91, nn.5-27.
[64] See
note 60, supra.
[65] See Performance
Bond Manual (Lawrence Lerner & Theodore M. Baum, eds. 2006) for a
summary of the law of performance bonds in the 50 states, the
[66] While
none of the discussions of the various surety performance bond options in
Section IV. of this paper go into any great detail concerning the surety’s risk
of loss in excess of the penal sum of the performance bond, many of the
secondary materials cited in the relevant footnotes do address this issue.
[67] Bruner & O’Connor on Construction Law,
§ 18:18.
[68] St. Paul Fire and Marine Ins. Co. v. City of
Green River,
[69] There are a
number of books, articles and papers that generally discuss the surety’s
performance bond options. The following
are relevant and helpful: Marilyn
Klinger, James P. Diwik & Kevin L. Lybeck, Contract Performance Bonds, in The
Law of Suretyship, 2d Ed. 83-91 (Edward G. Gallagher, ed. 2000); James
J. Mercier & John T. Harris, Rights
of the Surety in Event of Default, in The
Law of Performance Bonds 39-59 (Lawrence R. Moelmann & John T.
Harris, eds. 2000).
[70] When
the principal has been terminated on one construction project, the surety will
normally choose its option and stick with it (with the exception possibly being
the financing of its principal). When
the principal has been terminated from a number of construction contracts, the
surety may use a mix of its options, assuming that each of the performance
bonds allows various options. For
example, the surety may finance the principal’s completion of one or two of the
construction contracts while at the same time either take over and complete or
tender a completion contractor on others and work with the obligee (or “buy
back” the performance bond) on still other projects. Other than the terms and requirements that
may be found in each performance bond, the surety is entitled to mitigate its
loss at its discretion and is not required to take only one course of action
and use only one option when faced with multiple terminated construction
contracts.
[71] Gregory L. Daily & Todd C. Kazlow, Takeover and Completion, in Bond Default Manual, 3d Ed. 223-41 (Duncan
L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005); Bruce C.
King, Takeover and Completion of Bonded
Contracts by the Surety, 27 Brief
No. 1, 22 (1997); Gregory S. Arnold, Christopher Morkan & Matthew M.
Horowitz, Issues and Practical
Considerations for the Surety in Using Subcontractor Ratification Agreements
(unpublished paper submitted at the Seventeenth Annual Northeast Surety &
Fidelity Claims Conference on September 21, 2006); Luther P. Cochrane, Obligations of Principal’s Subcontractors
and Suppliers on Default or Takeover by Surety, 14 Forum 896 (1979); Michael J. Sugar, Jr., Elizabeth E. Spiker
& Richard D. Davis, Challenges of a
Unit Price Contract Re-Let (unpublished paper submitted at the Fifteenth
Annual Northeast Surety & Claims Conference on September 30, 2004).
[72] One
question with respect to the surety’s “agent” or “independent contractor” as
its completion contractor is whether the surety may use its principal or the
employees and other personnel of its principal to assist in the completion of
the construction project. At least one
court has held that the surety exercising its rights under paragraph 4.2 of the
AIA Document A312 Performance Bond may use the principal’s personnel as part of
its project team for the completion of the construction project even if the
obligee objects. St. Paul Fire and Marine Ins. Co. v. City of Green River,
[73] The
Bond Default Manual, 3d Ed. (Duncan
L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005) contains an
Appendix which includes as Exhibits 5.1, 5.2 and 5.3 sample Takeover
Agreements, and as Exhibit 5.4, a Completion Agreement with the federal
government at pp. 609-28; see also
the Takeover Agreement at Exhibit 8.1 on pp. 685-90.
[74] In
St. Paul Fire and Marine Ins. Co. v. City
of Green River,
[75] The
Bond Default Manual, 3d Ed. (Duncan
L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005) contains an
Appendix that includes as Exhibits 5.5 and 5.6 sample Completion Contracts at
pp. 629-48.
[77] Tammy Giroux
& Morgan W. Streetman, Limiting the
Takeover Surety’s Liability to the Bond Penal Sum (unpublished paper
submitted at the Seventeenth Annual Northeast Surety & Fidelity Claims
Conference on September 21, 2006). For
example, the Takeover Agreement may provide:
The total liability of the Surety under this Takeover Agreement
and the Performance Bond for the performance of the work, after the expenditure
of the Contract Balance, is limited to and shall not exceed the penal sum of
the Performance Bond in the amount of $_________. All payments properly made by the Surety for
the performance of the Original Contract shall be credited against the penal
sum of the Performance Bond. Nothing in
this Agreement constitutes a waiver of such penal sum or an increase in the
liability of the Surety under the Performance Bond.
[78] See
note 75, supra, concerning certain form Completion Contracts.
[79] E.A. “Seth,”
Mills, Jr. & Susan M. Moore, Tender,
in Bond Default Manual, 3d Ed.
243-67 (Duncan L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds.
2005) and the citations contained therein.
[80] The
Bond Default Manual, 3d Ed.
(Duncan L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005)
contains an Appendix that includes Exhibits 6.1 through 6.15, pp. 651-84, that
may assist the parties in a Tender Agreement situation.
[81] Francis J.
McGrath, George J. Bachrach & Adam Cizek, The Financing Surety as a Performing Surety - Law and Practice
(unpublished paper submitted at the Fourteenth Annual Northeast Surety &
Fidelity Claims Conference on September 18, 2003).
[82] George J.
Bachrach & Matthew L. Silverstein, Financing
the Principal, in Bond Default
Manual, 3d Ed. 155-221 (Duncan L. Clore, Richard E. Towle & Michael
J. Sugar, Jr., eds. 2005); Francis J. McGrath, George J. Bachrach & Adam
Cizek, The Financing Surety as a
Performing Surety - Law and Practice (unpublished paper submitted at the
Fourteenth Annual Northeast Surety & Fidelity Claims Conference on
September 18, 2003); T. Scott Leo, The
Financing Surety and the Chapter 11 Principal, 26 Tort & Ins. L.J. 45 (1990); Gilbert J. Schroeder, Providing Financial Support to the
Contractor, 17 Forum 1190
(1982); Gilbert J. Schroeder, Procedures
and Instruments Utilized to Protect the Surety Who Finances a Contractor,
14 Forum 830 (1979) (“Financing
is dangerous.”).
[83] Paragraph
4.1 of the AIA Document A312 Performance Bond requires the “consent of the
Owner” if the surety wants to finance the principal’s completion of the
construction contract, while paragraph 4.2 does not require the obligee’s
consent when the surety exercises its right to “[u]ndertake to perform and
complete the Construction Contract itself, through its agents or through
independent contractors,” and those “agents” or “independent contractors”
include the principal’s employees and other personnel. See St.
Paul Fire and Marine Ins. Co. v.
[84] The
Bond Default Manual, 3d Ed.
(Duncan L. Clore, Richard E. Towle & Michael J. Sugar, Jr., eds. 2005)
contains an Appendix that includes Exhibit 4.1, the Financing and Collateral
Agreement, along with several other agreements and related documents (Exhibits
4.1.2 through 4.1.7) at pp. 531-604.
[85] When,
however, the obligee’s actions do violate the surety’s rights under the
performance bond, the surety may be released and discharged from its obligations
under the performance bond. See
Section III. B. 2., supra.
[86] Deborah S.
Griffin & Stephen J. Beatty, Completion
by the Bond Obligee, in Bond Default
Manual, 3d Ed. 269-86 (Duncan L. Clore, Richard E. Towle & Michael
J. Sugar, Jr., eds. 2005) and the citations contained therein.
[87] See Section III. A. and B., including
B.2., supra.
[88] AIA
Document A312 Performance Bond, paragraph 4.4.2.
[89] The
AIA Document A312 Performance Bond, paragraph 5, provides:
If the Surety does not proceed as provided
in Paragraph 4 with reasonable promptness, the Surety shall be deemed to be in
default on this Bond fifteen days after receipt of an additional written notice
from the Owner to the Surety demanding that the Surety perform its obligations
under this Bond, and the Owner shall be entitled to enforce any remedy
available to the Owner. If the Surety
proceeds as provided in Subparagraph 4.4, and the Owner refuses the payment
tendered or the Surety has denied liability, in whole or in part, without
further notice the Owner shall be entitled to enforce any remedy available to
the Owner.
[90] In
Seaboard Sur. Co. v. Town of Greenfield,
266 F. Supp. 2d 189 (D. Mass. 2003), aff’d,
370 F.3d 215 (1st Cir.
2004), the court found that the
obligee failed to provide the surety with the 15 day notice of default on the
bond as required by paragraph 5, and that this constituted a material breach by
the obligee, which discharged the surety from any liability under the
performance bond as a matter of law.
Furthermore, in St. Paul Fire and
Marine Ins. Co. v. City of Green River,
[91] Some
performance bonds have dual obligee riders.
For example, if the obligee is the owner of a private construction
project, its construction lender that is providing the obligee with financing
for the project may become a dual obligee under the performance bond to give
the construction lender a right of recovery against the surety’s performance
bond. The construction lender’s damages
against the surety would not include the obligee’s financial obligations to the
lender under the loan. Rather, the dual
obligee bond gives both the obligee and the construction lender a direct cause
of action against the performance bond if the principal breaches the
construction contract and fails to perform.
Most dual obligee riders to performance bonds contain a savings clause
in favor of the surety that provides that any default by either of the obligees
relieves the surety from its performance obligations. See
generally Martha L. Perkins, The Rights and Obligation of the Surety
Under Dual Obligee Bonds (unpublished paper submitted at the Surety Claims
Institute annual meeting on June 23, 2005); Jay M. Mann, Dual Obligee Bonds - An Overview of the Surety’s Liability to
Co-Obligees (unpublished paper submitted at the ABA/TIPS Fidelity and
Surety Law Committee annual midwinter meeting on January 29, 1988); Thomas R.
Elliott, Jr., Dual Obligee Bonds - Some
Practical and Legal Considerations, 11 Forum
1229 (1976).
[92] Marilyn
Klinger, James P. Diwik & Kevin L. Lybeck, Contract Performance Bonds, in The
Law of Suretyship, 2d Ed. 100-05 (Edward G. Gallagher, ed. 2000).
[93] With respect
to the issue of whether an assignee of the obligee may assert rights against
the performance bond, see Benjamin D.
Lentz, Default, Notice of Default, Impact
Upon Surety’s Obligations Where Notice is Not Given, in The Law of Performance Bonds 31-35 (Lawrence R. Moelmann & John T.
Harris, eds. 2000).
[94] Marilyn
Klinger, James P. Diwik & Kevin L. Lybeck, Contract Performance Bonds, in The
Law of Suretyship, 2d Ed. 105-06 (Edward G. Gallagher, ed. 2000); John
H. Gregory & Michael Jay Rune, II., Liability
of the Performance Bond Surety (Under Contract of Suretyship), in The Law of Performance Bonds 37-40
(Lawrence R. Moelmann & John T. Harris, eds. 2000); Kevin L. Lybeck, The Performance Bond Surety’s Potential
Liability for Damages Suffered by Someone Other than the Obligee Named in the
Bond (unpublished paper submitted at the ABA annual meeting on August 13,
1991).
[95] However,
the AIA Document A311 Performance Bond does place a limitation on who may bring
an action under the performance bond as follows:
No right of action shall accrue on this bond
to or for the use of any person or corporation other than the Owner named
herein or the heirs, executors, administrators or successors of the Owner.
[96] The
AIA Document A312 Performance Bond, paragraph 7, provides:
The Surety shall not be liable to the Owner
or others for obligations of the Contractor that are unrelated to the Construction
Contract, and the Balance of the Contract Price shall not be reduced or set off
on account of any such unrelated obligations.
No right of action shall accrue on this Bond to any person or entity
other than the Owner or its heirs, executors, administrators or successors.
[97] Marilyn
Klinger, James P. Diwik & Kevin L. Lybeck, Contract Performance Bonds, in The
Law of Suretyship, 2d Ed. 81-118 (Edward G. Gallagher, ed. 2000)
(hereinafter “Klinger-Suretyship”); John H. Gregory & Michael Jay Rune, II,
Liability of the Performance Bond Surety
(Under Contract of Suretyship), in The
Law of Performance Bonds 123-49
(Lawrence R. Moelmann & John T. Harris, eds. 2000) (hereinafter
“Gregory - Performance Bonds”).
[98] Klinger
- Suretyship, pp. 107-08; Gregory - Performance Bonds, p. 133.
[99] Klinger - Suretyship, pp. 107-08 & 115-18; Gregory -
Performance Bonds, pp. 141-42; Samuel J. Arena, Jr., The Performance Bond Surety’s Liability for Latent Defect and Warranty
Claims (unpublished paper submitted at the Surety Claims Institute annual
meeting on June 24, 1999).
[100] Klinger -
Suretyship, pp. 108-10; Gregory - Performance Bonds, pp. 136-37; see also Darryl Weissman, Liability of the Performance Bond Surety for
Delay Damages, Consequential Damages and Liquidated Damages (unpublished
paper submitted at the Surety Claims Institute annual meeting on June 24,
1999).
[101] Klinger
- Suretyship, pp. 110-12, Gregory - Performance Bonds, pp. 133-35.
[106] See Bruner - Complex, p. 12, footnote 37,
which provides as follows:
See Bell
BCI Co. v. HRGM Corp., 276 F. Supp. 2d 462 (D. Md. 2003), in which a
subcontractor’s performance bond surety refused to perform following default of
its subcontractor principal. Rejecting
the contractor’s claims against the surety for tortious bad faith, the United
States District Court for the District of Maryland ruled that a “breach of
contract does not, under the circumstances of this case, give rise to a tort
action for bad faith.” The Court quoted
with approval a prior decision of the Maryland Court of Appeals holding as
follows:
[107] E.g., Transamerica Premier Ins. Co. v.
Brighton Sch. Dist. 27J., 940 P.2d 348 (
[108] R. Scott
Cochrane & Cole S. Kain,
Extra-Contractual Damages, in Bond
Default Manual, 3d Ed. 371-92 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005); Thomas J. Casamassima, Mark E. Aronson &
Frank E. Marchetti, Extra-Contractual
Damages, in The Law of Suretyship,
2d Ed. 393-418 (Edward G. Gallagher, ed. 2000); Lloyd N. Shields, Extracontractual Liability of Performance
Bond Sureties, in The Law of
Performance Bonds 151-77 (Lawrence R. Moelmann & John T. Harris,
eds. 2000).
[109] For a detailed
discussion of the principal’s construction contract claims as a potential
source of salvage for the surety, including the surety’s recovery rights to its
principal’s construction claims, the evaluation of the principal’s construction
claims (establishing the existence and the amount of the loss) and the types of
the principal’s construction claims (defective plans and specifications, change
conditions, delay claims, disruption claims, suspension of work claims,
acceleration claims and others), see
Patrick J. O’Connor, Jr., The Principal’s
Contract Claims as Salvage - A Primer, in Salvage
by the Surety 93-199
(George J. Bachrach, ed. 1998).
[110] George J.
Bachrach & John V. Burch, The
Surety’s Subrogation Rights, in The Law
of Suretyship, 2d Ed. 419-53 (Edward G. Gallagher, ed. 2000); Francis J.
McGrath, George J. Bachrach & Adam Cizek, The Financing Surety as a Performing Surety - Law and Practice (unpublished
paper submitted at the Fourteenth Annual Northeast Surety & Fidelity Claims
Conference on September 18, 2003); Edward G. Gallagher, Entitlement to Contract Proceeds, in The Law of Performance Bonds 61-75 (Lawrence R. Moelmann
& John T. Harris, eds. 2000); George J. Bachrach & Cynthia E.
Rodgers-Waire, The Surety’s Rights to the
Contract Funds in the Principal’s Chapter 11 Bankruptcy Case, 35 Tort & Ins. L.J. 1 (1999); Edward
G. Gallagher, Entitlement to Contract
Proceeds, in The Law of Payment
Bonds 223-47 (Kevin L. Lybeck & H. Bruce Shreves, eds. 1998); The Subrogation Database: Cases Concerning the Subrogation Rights of
the Contract Bond Surety (George J. Bachrach, ed. 1995).
[111] The Surety’s Indemnity Agreement - Law &
Practice (Marilyn Klinger, Gary Judd & George J. Bachrach, eds.
2002); Armen Shahinian, Marc Brown & Joseph Monaghan, Deciding to Litigate: The
Surety’s Recourse Against Its Principal and Indemnitors, in Managing and Litigating the Complex Surety
Case, 2d Ed. 115-72 (Philip L. Bruner & Tracey L. Haley, eds. 2007);
Armen Shahinian, The General Agreement of
Indemnity, in The Law of Suretyship,
2d Ed. 487-525 (Edward G. Gallagher, ed. 2000); Jay M. Mann, Exoneration and Quia Timet, in The
Law of Suretyship, 2d Ed 455-85 (Edward G. Gallagher, ed. 2000); G. Steven Ruprecht, Surety’s Rights and Remedies Against
Principals and Against Indemnitors Under the General Indemnity Agreement, in The Law of Performance Bonds 77-121
(Lawrence R. Moelmann & John T. Harris, eds. 2000); Stephen J. Trecker
& Luther S. Ott, The Agreement of
Indemnity - The Surety’s Handling of Contract Bond Problems: Administration and Resolution of Performance
Bond and Payment Bond Claims, in The
Agreement of Indemnity - Practical Applications by the Surety 5-92 (George J. Bachrach, ed. 1990)
and an unpublished paper submitted at the ABA/TIPS Fidelity and Surety Law
Committee annual midwinter meeting on January 27, 1989; Robert L. Lawrence,
Robert M. Wright, George J. Bachrach & William M. Dolan, III, The Agreement of Indemnity - The Surety’s
Handling of Contract Bond Problems: Enforcement of the Surety’s Rights Against
the Principal and the Indemnitors Under the Agreement of Indemnity, in The Agreement of Indemnity - Practical
Applications by the Surety 93-172 (George J. Bachrach, ed. 1990) and an
unpublished paper submitted at the ABA/TIPS Fidelity and Surety Law Committee
annual midwinter meeting on January 27, 1989; Linwood O. Perry, Jr. & Henry
J. Wallach, Salvage - The Surety’s Right
to Reimbursement Under the Indemnification Provisions of the Agreement of
Indemnity, in The Agreement of
Indemnity - Practical Applications by the Surety 173-221 (George J.
Bachrach, ed. 1990) and an unpublished paper submitted at the ABA/TIPS Fidelity
and Surety Law Committee annual midwinter meeting on January 27, 1989.
[112] Ronald F. Goetsch & Christopher
R. Ward, Deciding to Litigate: The Surety’s Recourse Against Third Parties,
in Managing and Litigating the
Complex Surety Case, 2d Ed. 173-258 (Philip L. Bruner & Tracey L.
Haley, eds. 2007); Patrick J. O’Connor, Jr., Deciding to Litigate: The Surety’s
Rights Against Property and Liability Insurers of the Obligee, Principal and
Subcontractors, in Managing and
Litigating the Complex Surety Case, 2d Ed. 259-429 (Philip L. Bruner
& Tracey L. Haley, eds. 2007); Christopher R. Ward & Mary Jean Pethick,
Considerations With Respect to Insurance
Coverage, in Bond Default Manual, 3d
Ed. 393-430 (Duncan L. Clore, Richard E. Towle & Michael J. Sugar,
Jr., eds. 2005); James D. Ferrucci & Ann Hester, The Architect as a Source of Salvage (unpublished paper submitted
at the Fifteenth Annual Northeast Surety & Fidelity Claims Conference on
September 30, 2004); James D. Ferrucci & Scott D. Baron, The Surety’s Claims Against Third Parties,
in Salvage by the Surety
209-62 (George J. Bachrach, ed. 1998); Martha Crandall Coleman, Design Professionals’ Liability for
Negligent Design and Project Management (unpublished paper submitted at the
ABA/TIPS Fidelity and Surety Law Committee annual midwinter meeting on January
24, 1997).
[113] For
example, pursuant to the AIA Document A312 Performance Bond, paragraph 9:
Any proceeding, legal or equitable, under
this Bond may be instituted in any court of competent jurisdiction in the
location in which the work or part of the work is located . . . .
[114] Gregory R.
Veal, Arbitration and the Performance
Bond Surety (unpublished paper submitted at the Surety Claims Institute
annual meeting on June 23, 2005); H. Bruce Shreves & Kevin L. Lybeck, Arbitration of Performance Bond Disputes, in
The Law of Suretyship, 2d Ed. 375-92
(Edward G. Gallagher, ed. 2000); James D. Ferrucci, Effect of an Arbitration Provision in the Principal’s Contract With the
Obligee, in The Law of Performance
Bonds 249-87 (Lawrence R. Moelmann & John T. Harris, eds. 2000); J.
Michael Franks & John W. Heacock, The
Contract Surety’s Involvement in and Preclusion by Arbitration Proceedings
Involving Its Principal: An Update With
Drafting Comments (unpublished paper submitted at the ABA annual meeting on
August 9, 1999); Robert W. Wright, The
Mediation Process (unpublished paper submitted at the ABA/TIPS Fidelity and
Surety Law Committee annual midwinter meeting on January 24, 1997); J. Michael
Franks & John W. Heacock, Arbitration
and the Contract Surety: Inclusion and
Preclusion (unpublished paper submitted at the ABA/TIPS Fidelity and Surety
Law Committee annual midwinter meeting on January 24, 1997).
[115] Robert J.
Berens & J. Blake Wilcox, Deciding to
Litigate: Representing the Surety in a Complex Bankruptcy Case, in Managing and Litigating the Complex Surety Case, 2d Ed. 501-80 (Philip L.
Bruner & Tracey L. Haley, eds. 2007); T. Scott
Leo & J. Blake Wilcox, Bankruptcy
Considerations and Bond Defaults, in Bond
Default Manual, 3d Ed. 313-69 (Duncan L. Clore, Richard E. Towle &
Michael J. Sugar, Jr., eds. 2005); Chad L. Schexnayder, Bankruptcy and the Surety, in
The Law of Suretyship, 2d Ed. 317-73 (Edward G. Gallagher, ed. 2000);
Chad L. Schexnayder, Bankruptcy, in The Law of Performance Bonds 289-331
(Lawrence R. Moelmann & John T. Harris, eds. 2000); George J. Bachrach
& Cynthia E. Rodgers-Waire, The
Surety’s Rights to the Contract Funds in the Principal’s Chapter 11 Bankruptcy
Case, 35 Tort & Ins. L.J.
1 (1999); T. Scott Leo, The Financing
Surety and the Chapter 11 Principal, 26 Tort
& Ins. L.J. 45 (1990).